UNITED STATES
DEPARTMENT OF LABOR
MINE SAFETY AND HEALTH ADMINISTRATION
District 10
ACCIDENT INVESTIGATION REPORT
(Preparation Plant)
Fatal Machinery
Dotiki Preparation Plant (I.D. No. 15-02132)
Webster County Coal Corp.
Clay, Webster County, Kentucky
September 11, 1995
by
Robert L. Meadows
Coal Mine Safety & Health Inspector
and
Darold Gamblin
Coal Mine Safety & Health Inspector
Originating Office - Mine Safety and Health Administration
100 YMCA Drive, Madisonville, Kentucky 42431-9019
Rexford Music, District Manager
GENERAL INFORMATION AND BACKGROUND
The Dotiki Preparation Plant is a surface facility located at
Clay, in Webster County, Kentucky. This plant, which processes
coal from one underground mine, includes a deep mine coal
stockpile area, a truck loading haulage road, and a coal train
loading point. The raw coal from the underground mine is
transported to the surface by a 5 foot belt conveyor, and then
deposited into two raw coal silos; one of which is of 5000 ton
capacity and the other a 1500 ton capacity. When necessary,
these two silos can be bypassed and coal transported directly
onto the raw coal stockpile. Coal from this stockpile is then
deposited via the No. 7 and No. 10 hoppers onto the draw off
tunnel conveyor belt, and transported approximately 500 feet to
the coal train loading point.
The plant employs 26 persons. Coal is processed on two
production shifts, five days each week, and maintenance is
conducted on third shift. As many as five trains, averaging from
50 to 75 rail cars each, are loaded weekly. The operation
processes an average of 12,500 tons of coal daily, and up to 3.1
million tons annually.
The principal officers of Webster County Coal Corp. are as
follows:
Joseph W. Craft, III.........President
James B. Gill....................Vice President
Alan Boswell....................Manager of Operations
Joel R. Reid......................Plant Manager
The last regular safety and health inspection was completed on
June 26, 1995. A regular inspection was ongoing at the time of
the accident.
DESCRIPTION OF ACCIDENT
On Monday, September 11, 1995, at approximately 7:00 a.m., the
Dotiki Preparation Plant crew began their scheduled day's work.
After conducting a safety meeting, Ricky Reid, plant foreman,
assigned work duties to the surface employees and informed them
that the first train to be loaded was expected to arrive at
approximately 10:00 a.m.
Brian Keith Liles (victim) was sent to the rotary breaker
building to inspect a water line which had been installed during
the weekend. Jeff Throgmorton, David Cowans, Bobby Daniels, and
Neil Rhye were assigned to inspect and clean the load out tunnel
before the train arrived. James Berry was sent to load coal
trucks using the 988 front end-loader. David Threlkeld, plant
electrician, was instructed to check the plant computer and
ensure that all other functions of the plant were operating
properly.
After checking the water line, Liles joined Throgmorton, Cowans,
and Rhye in cleaning and examining the draw off tunnel. After
they were finished, they went to the bathhouse to eat lunch.
The coal train arrived at 10:00 a.m., so the crew drove the
company pickup truck to the train loading point and inspected the
coal car hopper doors before loading. In preparation for loading
the train, Cowans took the D9L bulldozer to the top of the raw
coal stock pile and began pushing coal away from the west side of
the stacking tube to make room for additional coal. Throgmorton
drove Liles to the raw coal stockpile at about 10:30 a.m., where
Liles started the D9H dozer and trammed up the west side of the
raw coal stockpile.
As Liles approached the top of the stockpile, Cowans received
word over the radio that he was to drive the D9L dozer to the toe
of the stockpile and relieve Berry on the front end-loader.
Threlkeld then took Cowans' place on the D9L dozer and trammed
back up the stockpile where he encountered Liles. Using hand and
arm signals because of the noise, Liles indicated to Threlkeld
that he would go to the east side of the stockpile, and Threlkeld
should continue pushing coal on the west side. As Liles trammed
the dozer around the stockpile and out of sight, Threlkeld
noticed that the time was about 10:40 a.m. Also at 10:40 a.m.,
Jeff Throgmorton energized the tunnel fan, monitors, and charts,
started the No. 7 and No. 10 coal hoppers, and activated the draw
off tunnel conveyor belt to transport the raw coal into the first
train car.
Approximately 10 minutes later, Threlkeld noticed heavy smoke
rising from the other side of the stockpile near the stacker
tube. He reversed the bulldozer and attempted to see the source,
but the stacker tube blocked his vision. Grabbing his fire
extinguisher, Threlkeld stepped down from the dozer and walked
around the stockpile where he saw approximately 2 feet of the
blade of Liles' D9H dozer protruding from the coal, pointing
upward. The engine of the dozer was still running.
Threlkeld raced back to his dozer and radioed Throgmorton to shut
down the load out hoppers and bring help because Liles' dozer was
submerged in the coal. Surface Manager Reid heard the radio
transmission from the desk at his office. He immediately drove
to the 988 front end-loader and motioned for Cowans to follow him
up the coal pile. Throgmorton, Daniels, and Rhye also overheard
the reports of the accident over the radio and rushed to the
scene.
By the time that Reid arrived, the dozer had completely
disappeared beneath the surface of the coal pile. Reid directed
Rhye to notify Manager of Operations Allen Boswell and to call
for an ambulance. Webster County Ambulance Service and the Life
Flight Helicopter arrived shortly afterward.
Reid then told Throgmorton and Daniels to get steel ropes and
bring the other two dozers. Threlkeld began removing coal from
near the accident scene with D9L dozer, while Cowans assisted
with a D8N dozer. Berry started the 988 front end-loader and
proceeded to help.
At 11:58 a.m., Reid told Throgmorton to energize the load out
feeder in an attempt to remove some of the coal from around the
trapped dozer, but this activity was not productive and was
halted within a few minutes. The two dozers and front end-loader
continued their excavation efforts and, a short time later, the
blade of the trapped dozer was uncovered. The D8N dozer was then
hooked to the blade with a steel rope, but efforts to pull the
D9H free were unsuccessful. The D9L dozer was then hooked in
tandem with the D8N dozer and together, the two dozers pulled the
trapped dozer from the coal pile at 12:30 p.m.
As soon as the dozer was pulled free of the coal, Department of
Mines and Minerals Electrical Instructor Bill Perkins rushed to
the cab, uncovered the victim's face, and began mouth to mouth
resuscitation. Liles was then removed from the cab and the Life
Flight Crew continued resuscitation efforts at the accident site,
while keeping Welborn Hospital officials in Evansville, Indiana,
informed of the activities via radio. At 1:02 p.m., Liles was
pronounced dead by Dr. Lee Newbury from Welborn Hospital.
INVESTIGATION OF THE ACCIDENT
At 11:20 a.m., on September 11, 1995, CMSH Inspector George
Newlin notified Assistant District Manager Richard L. Reynolds by
telephone that a dozer and its operator were trapped in the raw
coal stock pile at the Dotiki Preparation Plant. Mine Safety and
Health personnel, supervised by Assistant District Manager
Reynolds, began arriving at 12:15 p.m., and assisted in the
recovery. A 103(k) Order was issued to ensure the safety of the
miners until the accident investigation could be completed.
The Mine Safety and Health Administration and the Kentucky
Department of Mine and Minerals jointly conducted an
investigation.
The Mine Safety and Health Administration and the Kentucky
Department of Mines and Minerals conducted interviews of five
individuals who had knowledge of facts surrounding the accident.
These interviews were conducted at the Webster County Coal Corp.,
Dotiki Mine training room at Lisman, Kentucky, on September 12,
1995.
The physical portion of the investigation was completed on
September 18, at 1400 hrs, and the 103(k) Order which had been
issued by the Mine Safety and Health Administration on September
11, was terminated.
TRAINING
The records indicated that all training had been conducted in
accordance with Part 48.
PHYSICAL FACTORS INVOLVED
The investigation revealed the following factors relevant to the
accident:
- There were no eyewitnesses to the accident.
- The raw coal stockpile where the accident occurred is
approximately 200 feet long, 175 feet wide, and 60 feet
high.
- The draw off tunnel is 525 feet long.
- The five raw coal feed hoppers are hydraulically controlled,
but only two of the hoppers were in use at the time of the
accident.
- All equipment on the raw coal stockpile was provided with
two-way communications.
- Coal had last been drawn through the No. 10 hopper on
September 7, 1995. Since that time, approximately 15,000
tons of coal had been deposited onto the raw coal stock
pile.
- On the morning of September 11, four railroad cars had been
loaded before the accident occurred.
- The victim had been pushing coal on top of the raw coal
stock pile for approximately 10 to 15 minutes before the
dozer fell into the No. 10 hopper.
- The Pressure Loadout Feed Chart established that the No. 10
hopper was activated at approximately 10:43 a.m., and was
stopped after the accident was discovered at about 10:55
a.m.
- The Pressure Loadout Feed Chart also confirmed that the No.
10 hopper was reactivated at approximately 11:59 a.m. in an
attempt to remove coal from around the trapped dozer, and
then de-energized again at 12:01 p.m. when this effort
failed.
- The rear glass, side glass, door glass, and front windshield
of the driver's compartment collapsed as the dozer submerged
into the coal pile, allowing the cab to fill with loose
coal.
- The Kentucky Medical Examiner established suffocation as the
cause of death.
- Company procedures prohibited the operation of dozers above
hoppers during loading operations. These procedures were
verbal, however, and had not been prescribed in any written
form.
- Statements from workers established that they had been
informed by management of the hazards of operating equipment
above hoppers during loading operations. Workers also
described the victim as being a particularly safety-minded
individual who habitually took extraordinary steps to remain
aware of his work related surroundings.
- After the accident, the company implemented the following
precautions;
- A radio check system was established to ensure that
communications procedures among the workers are
functional.
- The loadout operator is required to notify personnel
operating equipment on the stockpile before loading
operations commence.
- In order to provide dozer operators with an oxygen
source in case of entrapment, a one hour self contained
self rescuer (SCSR) will be kept in the cab of each
dozer.
- The company is studying the feasibility of placing
metal grids over cab windows to prevent their collapse
in the event of an entrapment.
CONCLUSION
The accident sequence began when the loadout operator energized
the No. 10 hopper. The potential was increased when the victim
trammed the dozer onto the raw coal above this hopper. The
accident occurred when the dozer that the victim was operating
fell into a hidden cavity which had opened as coal was drawn
through the No. 10 coal hopper.
VIOLATIONS
- 103(k) Order No. 4062007 was issued to assure the safety of
all persons in the affected area.
- No violations of 30 CFR were observed during this
investigation.
Respectfully submitted:
Robert Meadows
Coal Mine Safety and Health Inspector
Donald Gamblin
Coal Mine Safety and Health Inspector
Approved by:
Rexford Music
District Manager
District 10
Related Fatal Alert Bulletin: [FAB95C29]
|