UNITED STATES
DEPARTMENT OF LABOR
MINE SAFETY AND HEALTH ADMINISTRATION
Rocky Mountain District
Metal & Nonmetal Mine Safety and Health
ACCIDENT INVESTIGATION REPORT
SURFACE METAL MINE
FATAL ELECTRICAL ACCIDENT
Phelps Dodge Morenci, Incorporated (mine)
Mine I.D. No. 02-00024
Phelps Dodge Morenci, Incorporated
Morenci, Greenlee County, Arizona
October 31, 1995
By
Lee D. Ratliff
Supervisory Mine Safety and Health Inspector
Danny A. Frey
Mine Safety and Health Inspector
Originating Office
P.O. Box 25367 DFC
Denver, CO 80225-0367
Robert M. Friend
District Manager
GENERAL INFORMATION
Lance Dru Nohl, instrumentation electrician, age 30, was severely
burned and shocked on October 31, 1995, at approximately 12:01
p.m., when he was working inside a confined high voltage fuse
compartment within close proximity to energized 13,800 volts
(13.8kv) terminals. He died on November 1, 1995. Nohl had a
total of 6 years and 3 months mining experience, 2 years and 2
months at this mine as an instrumentation electrician.
The Rocky Mountain District MSHA office, Denver, Colorado was
notified of the accident on October 31, 1996, at 3:00 p.m., by a
phone call from Harold L. Boling, safety and hygiene supervisor,
Phelps Dodge Morenci, Inc. An investigation was started on
November 1, 1995.
The mine, owned and operated by Phelps Dodge Morenci, Inc., was
located at 4521 U.S. Highway 191, Morenci, Greenlee County,
Arizona. Copper ore was drilled, blasted and loaded on trucks
by electric-powered shovels. Ore then was transported to various
locations throughout the mine for crushing/milling. Total mine
employment was 2,475 persons. The work schedule was 3, 8-hour
shifts a day, 7 days a week.
Principal operating officials for Phelps Dodge Morenci, Inc.
were:
Timothy R. Snider, president
Donald J. Quinn, mine manager
Harold L. Boling, safety and hygiene supervisor
The training plan required by 30 CFR, Part 48, Subpart A was
approved on May 11, 1979, and revised October 19, 1993.
The last regular inspection at this operation was completed on
September 26, 1995.
PHYSICAL FACTORS INVOLVED
The accident occurred inside the 001 high voltage fuse
compartment located in the switchgear room at the southside
electrical substation (Appendix 3). A draw-out carriage inside
the compartment contained fuse protection for a single phase
control power transformer (CPT), which was located behind the 001
fuse compartment. Short circuit and ground fault protection for
the CPT were 15E ampere fuses, type EJ-O-ID.
Primary input voltage to the 50 kilovolt amperes CPT was 13.8 kv.
Secondary voltage was single phase 120/240 volts, alternating
current (ac). With the fuse carriage rolled in place and
engaged, a 13.8 kv fused circuit was provided to the primary of
the CPT.
Inside dimensions of the compartment with the fuse carriage
removed were 24 inches high by 40 inches deep by 36 inches wide.
Located inside the 001 fuse compartment was an insulated moveable
shutter board guarding four high voltage bushings. Stab
connectors were bolted to the top of each bushing for mating to
the fuse carriage pressure terminals. Center phase bushings were
not used as single phase service was required for the CPT
(Appendix 4).
The top two bushings were for the incoming 13.8 kv "line" side
and were mounted 18-1/8 inches apart, horizontally. The bottom
two bushings were connections for the "load" side of the fuse
carriage and the primary H1 and H2 leads for the CPT. Distance
between the top and bottom bushings was 8-1/8 inches, vertically.
However,oversized lugs had been installed on each bushing stab
terminal which reduced the flashover distance between the top and
bottom 13.8 kv terminals from 8-1/8 inches to 3-1/2 inches.
Primary power to the southside substation was 46,000 volts ac
which was transformed (stepped down) to 13.8 kv. The 13.8 kv was
fed to the switchgear room for additional circuit distribution
and further transformation for control power, lighting, and
battery charging systems. The southside substation and
switchgear room also provided high voltage power for the
southside solvent extraction-electrowinning (SX-EW) facilities.
Control power for the 13.8 kv substation switchgear room was
supplied by two 50 kva single phase CPT's that were located in
identical compartments directly behind the fuse carriages in
compartment numbers 001 and 002.
Transformer secondary power was fed to a single phase 120/240 vac
distribution panel at the switchgear room. One branch circuit
provided 120 vac to a direct current (dc) rectifier charging unit
which provided continuous charging for a bank of batteries
located in the switchgear room. The batteries supplied 125 volt
dc power to operate the 13.8 kv switchgear controls and
associated devices for the substation when a loss of power
occurred.
On the day of the accident electricians had been troubleshooting
loss of control power in the southside substation switchgear
room. They discovered primary control fuses on the H2 leads for
001 and 002 transformers had blown. Insulation had burned off
the 15 kv primary H2 leads to both transformers which allowed
contact with grounded metal compartment frames.
Blown fuses caused an interruption of power to the battery
charging units. After a period of time, the batteries discharged
and could not provide dc control power to operate the switchgear.
When the accident occurred protective devices at the 13.8 kv
switchgear room were not operable and the electrical fault was
opened at the powerhouse by a time delay, phase overcurrent relay
which monitored the 46,000 volt powerline. Employees stated that
all lights dimmed and estimated the fault lasted approximately 2
to 2« seconds. (Note: Normally, a fault of this magnitude should
be cleared in approximately 1/10 of a second.)
A violent electrical arc and explosion occurred inside
compartment 001 that charred most of the interior compartment
walls, components, and insulating shutter boards at the back of
the cubicle. The shutter mechanism was designed to slide up to
expose the stabs. Bolt heads used to secure the stabs and
terminal lugs onto the high voltage insulated bushings could be
accessed by removing the shutters or by raising the outer shutter
to align access windows with the stabs (Appendix 6). Following
the accident the moveable shutter was observed in the down
(closed) position.
The high voltage switchgear was installed in June 1995, and
placed in service approximately 3 months prior to the accident.
DESCRIPTION OF THE ACCIDENT
Lance Dru Nohl, victim, and Tom Crawford, electrician, reported
for work on day shift at 7:00 a.m., October 31, 1995. After
receiving work instructions from Wayne Spivey, instrumentation
electrical supervisor, Nohl began checking "current metering" on
rectifiers at the southside SX-EW facilities.
Crawford began scheduled substation maintenance checks as
assigned by Jim Denton, electric shop supervisor. At
approximately 9:30 a.m., Crawford arrived at the southside
substation and discovered that batteries for the 125 volt dc
control power for the high voltage switchgear were discharged.
He also observed that the 120/240 volt dc control power and
lighting systems were not functioning. Crawford reported the
condition to Denton.
Meanwhile, Nohl reported to Spivey that all indicating lights
for the feeder breakers at the southside SX-EW were out due to a
loss of dc control power.
Nohl proceeded to the southside substation switchgear room to
investigate the power problem and found Crawford investigating
the same condition. Both workers began troubleshooting.
The electricians located compartments 001 and 002 which housed
the 120/240 volt breakers for the control power circuitry and the
13.8 kv fused draw-out carriages. They locked out the single
phase 120/240 breakers and unlocked the fuse carriages. Crawford
rolled out the carriages from compartments 001 and 002.
Testing of the fuses revealed that the H2 lead was open (blown)
for each transformer. At approximately 10:00 a.m., Nohl reported
to Spivey that they needed fuses and to ask him where the
transformers were located. Spivey informed Nohl the transformers
were located in the compartments directly behind 001 and 002
carriage compartments.
Spivey arrived at the switchgear room and found that the
electricians had removed the cover plates from both transformer
compartments. Nohl, Crawford, Spivey and David Ogonowski,
electrical engineer, gathered around the transformers to observe
and discuss the problem.
Observations revealed the following conditions:
- The 15 kv primary H2 leads between the wall isolation bushing to both transformers had most of the insulation burned/melted off.
- Exposed bare copper conductor had contacted the grounded metal compartment frame which had caused the fuses in the H2 leads to blow in both transformer primaries.
- Non-shielded conductors used for the 15 kv H2 primary leads laying on metal surfaces in the compartments created a "corona effect" that caused excessive heating which burned off the insulation.
Spivey instructed Nohl and Crawford to test the 002 transformerto ensure it was in operating condition. He also told them toevaluate what would be necessary to replace the burned H2 lead onthe 002 transformer with the undamaged H1 lead from the 001transformer. Spivey and Ogonowski left the area. Nohl and Crawford tested the 002 transformer and determined theprimary windings were defective. They tested the 001 transformerand thought it was also defective because the secondary windingshowed "grounded". Further observation revealed that the neutralgrounding connection was still connected to the transformerterminals, resulting in a "grounded" reading. Afterdisconnecting the secondary leads, a followup test indicated thetransformer was not defective. At approximately 12:00 p.m., Crawford was reconnecting thesecondary leads to the 001 transformer when he heard a sizzlingsound followed by a flash and violent explosion that occurredbehind the wall directly in front of him, where Nohl had beenworking in the 001 fuse compartment. Crawford reported that theexplosion knocked him down and dazed him briefly. He ran aroundto the front of the switchgear compartments to check on Nohl. John Eddy, Brown and Root electrical contractor superintendent,was standing outside the substation switchgear room when he heardthe explosion. He ran inside and observed Nohl through thesmoke. Eddy, unsure of what happened and not knowing if Nohl wasclear of the voltage source, asked Nohl to come out of thecompartment area. Eddy assisted Nohl outside. A medic arrived on the scene and administered first aid. Nohlwas taken to a local hospital and later air-lifted to a burncenter in Phoenix, Arizona. He died the following day as aresult of burns received over 63 percent of his body. Crawford experienced head and muscle pain and was transported toa health care facility for observation. He was released laterthat same day. CONCLUSIONThe direct cause of the accident was failure to deenergize the13.8 kv feeder bus prior to working in the high voltagecompartment.
VIOLATIONSThe following order was issued during the investigation:
Order No. 4650214, 103 (k) Issued 10/31/96, at 1520 hours.
The company experienced an electrical accident that involved an employee (instrument electrician) receiving serious burns and possible electrical shock. The victim and another employee (electrician) were performing repairs on the switch gear located in the southside electrical substation switch gear room. This substation is the source of power to the southside tank house.
This order was issued to protect employees and to prevent unauthorized entry.
Terminated 11/1/95, at 1200 hours. The following citation was issued as a result of theinvestigation:
Citation No. 4665702, 104 (a) Issued 3/6/96, at 0915 hours for a violation of 30 CFR Part 56.12017.
On October 31, 1995, an instrumentation electrician was seriously injured in an accident at the south side substation switchgear room in high voltage compartment 001. The victim died on November 1, 1995, as a result of burns he received over 63 percent of his body. MSHA investigation has determined the 13.8 kv feeder bus was not deenergized before the victim entered the 001 fuse carriage compartment, nor were other preventative measures taken to safely isolate the energized terminals. The victim was working within close proximity of exposed energized 13.8 kv high voltage terminals inside the fuse compartment. High voltage hot-line equipment was not utilized.
Respectfully submitted by:
/s/ Lee Ratliff Supervisory Mine Safety and Health Inspector
/s/ Danny A. Frey Mine Safety and Health Inspector
Approved by,
Robert M. Friend District Manager Related Fatal Alert Bulletin: [FAB95M41]
|