UNITED STATES
DEPARTMENT OF LABOR
MINE SAFETY AND HEALTH ADMINISTRATION
District 4
REPORT OF INVESTIGATION
(UNDERGROUND COAL MINE)
FATAL ROOF-FALL ACCIDENT
Maple Meadow Mine (ID No. 46-03374)
Maple Meadow Mining Company
Fairdale, Raleigh County, West Virginia
June 26, 1996
by
Vaughan Gartin
Coal Mine Safety and Health Inspector
Originating Office - Mine Safety and Health Administration
100 Bluestone Road, Mount Hope, West Virginia 25880
Earnest C. Teaster,Jr., District Manager
OVERVIEW
General Information
The Maple Meadow Mine, Maple Meadow Mining Company, is located at
Fairdale, Raleigh County, West Virginia. The mine is developed
from the surface by one slope and four shafts. The mine is in
the Beckley seam that averages 84 inches in height.
The mine opened in May 1974. Employment is provided for 390
employees on two production shifts and one maintenance shift,
with the mine producing coal 7 days a week. The mine produces an
average of 7,500 tons of raw material daily from five continuous-
mining-machine sections, with two spare sections.
Coal is transported from the sections to the surface via belt
conveyors. The immediate roof consists of shale and the main
roof of sandstone and is primarily supported with 60-inch fully
grouted resin bolts. The roof bolts are installed on 4-foot
lengthwise and 4- to 5-foot crosswise spacing with 6- by 6-inch
bearing plates. Ventilation is induced at this mine by four
exhausting fans and one bleeder fan. At the No. 1 shaft, an 84-
inch fan produces 437,858 cubic feet of air a minute (CFM). At
the No. 2 shaft, an 84-inch fan produces 578,618 CFM. At the No.
3 shaft, another 84-inch fan produces 1,203,840 CFM. At the No.
4 shaft an 88-inch fan produces 194,940 CFM. The No. 1 bleeder
fan, a 56-inch fan produces 36,869 CFM. During the last AAA
inspection completed on June 19, 1996, by the Mine Safety and
Health Administration (MSHA), 3,004,285 cubic feet of methane was
liberated per 24-hour period. The existing roof control plan was
approved by MSHA on August 30, 1994.
DESCRIPTION OF ACCIDENT
James C. Herron, section foreman on the 2144 section, and his
crew departed from the surface at 6:55 a.m. The crew traveled on
the elevator to the bottom of the mine portal where they loaded
onto track-mounted, battery-powered man trips and traveled to the
section. Arriving on the section at 7:35 a.m., Herron discussed
a portion of the roof control plan with the crew at the dinner
hole. He then proceeded to the face areas (pillar line); met
with Mike Miller, the third-shift foreman; checked the face
areas; and held a discussion with Miller regarding mining
activities on the third shift. Herron traveled back to the
dinner hole and informed the crew that mining activities would
commence in the No. 14 lift of the No. 132 pillar block. Mining
activities commenced around 7:55 a.m. from the No. 3 entry in the
No. 14 lift of the 132 pillar block. Upon completion of the No.
14 lift, the miner crew moved to the No. 15 lift of the 131
pillar. Problems were encountered with the coal feeder while
mining these lifts and repair work was done, and the feeder was
operated manually as needed. Also, a hydraulic fitting was
broken off the left side ripper jack assembly and had to be
replaced. These repairs took about 20 minutes. After repairs
were made, mining commenced in the No. 16 and 17 lifts and on to
the pushout of Pillar 131. The actual mining only got two lifts
from the crosscut of Pillar 131 and then went to the pushout on
Pillar 131.
During mining of the pushout, the mine floor had to be loaded out
in conjunction with the pushout to prevent the remote-control
continuous-mining machine from hanging up when the coal bottom
broke up. Coal bottom was encountered at different locations on
this section. At about 11:00 a.m., while loading the fourth
shuttle car of coal from the pushout, the section foreman, who
was located in the crosscut on the left side of the mining
machine observing the mine roof, heard a crack or thump, and the
mine roof began to fall. The continuous-mining-machine operator,
Troy E. Henderson, and the continuous-mining-machine helper, Dan
Taylor, were positioned inby the corner of the outby pillar
block, when the mine roof started to fall right to left in the
crosscut and through the intersection at the final pushout. Both
the operator and helper started to run. Taylor was hit by a
piece of rock and knocked to the mine floor. He could not see
anything due to the dust generated by the fall of roof. Taylor
stated that he heard Troy Henderson say, "Get me out from under
here." When the dust subsided, Taylor saw Troy Henderson
underneath the falling rock, called for help, and proceeded to
remove a rock from the victim's head and shoulder area. Larry
Reedy, who was a roof-bolting-machine operator and an EMT, came
to the scene and checked the victim for vital signs. None were
found. The section foreman notified surface personnel, via
telephone, of the accident and requested assistance. He then
traveled back to the area of the fall, where he directed the crew
to obtain more timbers and material to secure the area for safety
reasons. Additional timbers were set and lifting jacks were used
to remove the victim. After the victim was removed and placed on
a stretcher, he was transported to the surface. Upon arriving on
the surface, he was placed in the care of the Trap Hill Volunteer
Fire Department and transported to the Raleigh General Hospital,
where he was pronounced dead on arrival.
INVESTIGATION OF ACCIDENT
The Mine Safety and Health Administration (MSHA) was notified at
11:40 a.m. on June 26, 1996, that a fatal roof-fall accident had
occurred. MSHA personnel arrived at the mine at 12:30 p.m. A
103(k) Order was issued to ensure the safety of the miners.
MSHA and the West Virginia Office of Miners' Health, Safety and
Training jointly conducted the investigation with the assistance
of mine management personnel, the miners, and representatives of
the miners.
All parties were briefed by mine management personnel as to the
circumstances surrounding the accident.
On June 26, 1996, representatives from all parties conducted the
on-site portion of the investigation. Photographs were taken and
relevant measurements and sketches were made of the accident
site.
Interviews of individuals known to have direct knowledge of the
facts surrounding the accident were conducted at the Maple Meadow
Mining Company training office at Fairdale, West Virginia, on
June 27, 1996.
The physical portion of the investigation was completed June 27,
1996, and the 103(k) Order was terminated.
DISCUSSION
Training
Records indicate that training had been conducted in accordance
with 30 CFR, Part 48.
An examination of Mr. Henderson's training records revealed that
he had received all required training.
Roof Control
The approved roof control plan allows the following types of roof
bolts to be used at the mine: conventional, full-grout, tension-
grout, and combination bolt systems.
The mine roof in the area where the accident occurred, as well as
other areas on the section, was supported with 60-inch full-grout
bolts.
The roof bolts were installed on 4- to 5-foot crosswise and 4-
foot lengthwise spacing as required by the approved roof control
plan.
Investigators observed that the timbers being utilized on the
section where pillar recovery work was being performed, were set
as required by the approved roof control plan, to the extent that
the area was accessible. The roof conditions and size of the
fall prevented investigators from seeing where the timbers were
set around the pushout.
Entries and crosscuts were developed 20 feet wide in accordance
with the approved roof control plan. Second mining was being
performed in the area where the accident occurred.
A Joy 14CM15 continuous-mining machine that was equipped with a
remote-control system was used on the 2144 section. Depths of
cuts were limited to 20 feet.
Physical Factors
The fall at the accident site measured 30 feet wide, an
undetermined length due to the pillar line, and 4 inches to 7
feet in thickness.
The pillars on this section were on 70- by 90-foot centers and
normally controlled the roof.
Maps of the 2144 section showed some blocks inby the pillar line
partially mined, and others fully mined on the same row of
blocks. This area had poor roof conditions and forced the
operator to leave coal where unstable roof was encountered.
There were no indications of excessive pressure on the pillars in
the immediate area surrounding the roof fall or the rest of this
section. Some minor floor heave was observed in the immediate
area, but not elsewhere on the section.
The mine roof was bolted with 5-foot resin-grouted bolts.
Due to the size of the fall, the exact location of all timbers
set for mining the pushout could not be determined. People
interviewed said that the timbers were set according to the plan.
The final pushout normally consisted of 10 to 12 shuttle cars of
coal.
Parts of Pillars 131 and 132 were mined 7 hours previous to
mining on the day shift. With the mine roof standing, the lifts
in Pillars 131 and 132 were then mined before the pushout of
No. 131.
The location of the continuous-mining machine operator/helper,
while mining the final pushout, was just inby the corner of the
outby pillar.
Coal bottom was being mined throughout this section, including
the final pushout of the 131 pillar block, to prevent the
continuous-mining machine from hanging up.
A Joy 14CM15 continuous-mining machine with radio-remote control
was being used.
The Joy 14CM15 continuous-mining machine was covered in a roof
fall a week prior to this accident. It was being trammed out of
an area where the roof was working. The remote operator was in a
safe location when an intersection fell on the miner.
CONCLUSION
The fatal accident occurred as a result of a premature roof fall
caused by a combination of poor roof conditions and extended time
to mine Pillar 131, which sat 7 hours between shifts. The
operator and helper were located inby the corner of the outby
pillar block when, with little or no warning, the mine roof caved
right to left in the crosscut and through the intersection at the
final pushout, causing fatal crushing injuries to the continuous-
mining-machine operator.
CONTRIBUTING VIOLATIONS
There were no contributing violations of 30 CFR cited during the
investigation of the fatal roof-fall accident.
Respectfully submitted by:
Vaughan Gartin
Coal Mine Safety and Health Inspector
Approved by:
Richard J. Kline
Assistant District Manager
Earnest C. Teaster, Jr.
District Manager
Related Fatal Alert Bulletin: FAB96C18
|