UNITED STATES
DEPARTMENT OF LABOR
MINE SAFETY AND HEALTH ADMINISTRATION
Southeastern District
Metal and Nonmetal Mine Safety and Health
Accident Investigation Report
Surface Nonmetal Mine
Fatal Falling/Sliding Material Accident
Bullitt County Stone Company
Rogers Group, Incorporated-Bullitt County Stone Company
Shepherdsville, Bullitt County, Kentucky
I.D. No. 15-00008
July 17, 1996
By
J. B. Daugherty
Supervisory Mine Inspector
And
E. G. Duarte
Mine Safety and Health Inspector
Originating Office
Mine Safety and Health Administration
135 Gemini Circle, Suite 212
Birmingham, Alabama 35209
Martin Rosta
District Manager
GENERAL INFORMATION
Joyce C. Gerwitz, welder, age 38, died of suffocation at
about 5:05 p.m. on July 17, 1996, when she was engulfed by a
slide of material while cutting an opening at the end of a
pug mill surge tunnel. She had a total of 9 days mining
experience, all with this company. The victim had received
training in accordance with 30 CFR Part 48. Eight hours had
been completed on July 10, 1996.
MSHA was notified at 5:20 p.m. on the day of the accident by
a telephone call from Darin Matson, area production manager.
An investigation was started the same day.
The Bullitt County Stone Company, a crushed limestone
quarry, owned and operated by Rogers Group, Incorporated-Bullitt County Stone Company, was located just north of
Shepherdsville, Bullitt County, Kentucky. The principal
operating official was George Newlin, quarry superintendent.
The quarry was normally operated two, 8-hour shifts a day, 5
days a week. A total of 17 persons was employed.
Limestone was mined by a multiple bench mining system using
conventional quarrying methods to drill, blast, load, and
haul the material to a plant where it was crushed and sized.
The final product was used in road building material.
The last regular inspection of this operation was completed
on March 13, 1996.
PHYSICAL FACTORS
The surge pile where the accident occurred consisted of
approximately 15,000 tons of dense graded aggregate
material. A reclaim tunnel which was constructed of steel,
measured 9 feet in diameter, 50 feet long and was under the
surge pile . The tunnel declined at an approximate 10-12
degree angle, with the lower end enclosed and housed a
conveyor belt which transported material from the surge pile
to the pug mill.
Two Michigan front-end loaders, a L270 and a L320, were used
to excavate an approximate 25 foot wide cut in the surge
pile at the rear of the tunnel to expose the enclosed end of
the tunnel. This excavation left vertical banks above and
around the tunnel end which were approximately 35 feet high.
DESCRIPTION OF ACCIDENT
On the day of the accident, Joyce C. Gerwitz, (victim),
reported for work at 7:00 a.m., her regular starting time.
She was assigned to do routine maintenance and welding.
Shortly after the shift started, Charles (Eddie) Weber, pug
mill operator, informed Thomas Jewell, quarry foreman, that
a major spillage had occurred which filled the inside lower
end of the reclaim tunnel and covered the tail section of
the conveyor belt. At about 9:30 a.m., Gerwitz and three
other employees were instructed by Jewell to clean up the
spillage. The employees reportedly were directed to enter
the tunnel and take the spilled material out of the entrance
in buckets.
Because this was tedious and time consuming, Weber suggested
to Jewell that it would be faster to wash the spillage from
inside the tunnel to the outside rather than carry the
material out in buckets. Weber told Jewell that this had
been done in the past when a spill occurred inside the
tunnel. Weber further told Jewell that in order to wash the
material out, a cut would have to be made in the surge pile
to expose the lower end of the tunnel so the material would
have room to flow out of the tunnel.
Shortly before noon, Jewell instructed two front-end loader
operators to remove the material covering the surge pile end
of the tunnel. While the area was being excavated,
employees continued to carry material out to access the
inside lower end of the tunnel to make the cut and wash out
the spillage.
When Darin Matson, area production manager, and George
Newlin, quarry superintendent, were making rounds, Weber
informed them that the excavation was going well and that he
could see the top of the tunnel. Weber further told them
that once the area was clear, he would get the Bobcat loader
to clean up the material that would be washed out of the
tunnel. Matson and Newlin told Weber that he was not to use
the Bobcat loader because the material would cover him if it
sloughed. They instructed Weber that after the excavation
was completed all work was to be done from inside the tunnel
so employees would not be exposed to the unstable material.
At about 4:45 p.m., Gerwitz and Timothy Smolenski, quality
control, were working inside the tunnel when John Williams,
maintenance leadman, arrived with a welding truck at the
tunnel entrance. Gerwitz, Smolenski, and Williams strung
out cutting torch hoses into the tunnel in preparation to
cut an opening at the rear of the tunnel. A short time
later, Weber arrived at the tunnel entrance and told them to
remove the hoses because he wanted them to cut the opening
in the tunnel from outside, which was reportedly contrary to
instructions previously given to Weber by Matson and Newlin.
The hoses were placed back in the welding truck and Gerwitz
and Weber drove around to the excavated area at the exposed
end of the tunnel. Williams left the site and Smolenski
stayed to take a water hose inside the tunnel before walking
around to where Weber and Gerwitz were. Weber told
Smolenski to go to the shop and bring back the Bobcat loader
to be used to remove the washed out material, which again
was not what Weber had been instructed by management to do.
Gerwitz walked about 50 feet into the excavated area toward
the tunnel while Weber stayed about 15 feet behind her to
watch for sloughing. After Gerwitz began cutting, Weber
suggested that they make a trial run to ensure that she
could get away from the area in the event the material
sloughed. When Weber yelled, Gerwitz ran out of the
excavated area. This exercise was done twice before she
returned to the exposed end of the tunnel to continue
cutting.
A short time later Smolenski returned and parked the Bobcat
and Weber instructed him to also act as a spotter.
Smolenski walked up and stood about 6 feet behind Weber.
Gerwitz had knelt down and began cutting when the right side
of the bank sloughed. Smolenski yelled for Gerwitz to get
out, but she was unable to escape and was covered by an
estimated 40 tons of material. Weber was buried to his
waist. Smolenski attempted to uncover him with his hands,
but realized that he could not get Weber out. Smolenski ran
to the area overlooking the shop and yelled to George
Newlin, who immediately radioed for help. A front-end
loader was used to free Weber. Approximately 30 minutes
later, Gerwitz's body was recovered. She was pronounced
dead at the scene by the county coroner. Cause of death was
attributed to suffocation.
CONCLUSION
The cause of the accident was the failure to properly slope
or support the stockpile banks that surrounded the pug mill
tunnel before entering the area.
VIOLATION
Citation No. 4522006
Issued on July 19, 1996, under the
provisions of 104(a) for a violation of Standard 56.9314:
A welder was fatally injured when she was buried
under a slough of material estimated at 40 tons of
dense graded aggregate. The pug mill operator was
partially buried but not seriously injured. The
welder was in the process of cutting out the metal
plate at the end of the surge tunnel when the
slide of material occurred. The back wall had not
been sloped or supported in any manner.
This citation was terminated on July 19, 1996.
The area was barricaded and filled in.
/s/J. B. Daugherty
Supervisory Mine Inspector
/s/ E. G. Duarte
Mine Safety and Health Inspector
Approved by: Martin Rosta
District Manager
Related Fatal Alert Bulletin: [FAB96M29]
|