UNITED STATES
DEPARTMENT OF LABOR
MINE SAFETY AND HEALTH ADMINISTRATION
NORTHEASTERN DISTRICT
Accident Investigation Report
Surface Nonmetal Mine
Fatal Fall of Ground Accident
Hall Explosives Inc.
Contractor No. GM8
at
Global Stone PenRoc Inc.
PenRoc
York, York County, Pennsylvania
I.D. No. 36-00184
December 17, 1996
By
Dennis Yesko, Supervisory Mine Safety and Health Inspector
and
Edward F. Skvarch, Mine Safety and Health Inspector
Northeastern District
Mine Safety and Health Administration
230 Executive Drive, Suite 2
Cranberry Township, Pennsylvania 16066-6415
James R. Petrie, District Manager
GENERAL INFORMATION
Ronald Kimmel, Jr., senior blaster/sales representative, age 36, was fatally injured at
approximately 11:10 a.m., on December 17, 1996, when the ground on which he was
standing collapsed. Kimmel was employed by Hall Explosives, Inc., an independent
contractor that specialized in blasting. He had a total of 5 years 8 months mining
experience all with this contractor, the last year as a senior blaster. Kimmel was trained
in accordance with 30 CFR, Part 48. This training addressed examination of ground for
hazardous conditions.
Brian Glackin, environmental and safety engineer for Global Stone PenRoc Inc., notified
MSHA on the day of the accident. The accident investigation was started the next day.
PenRoc was a surface, crushed stone operation with an associated mill. The operation
was owned and operated by Global Stone PenRoc Inc., located in York, York County,
Pennsylvania. The principal operating official was William Vest, general manager. The
facility normally operated one, 9-hour shift per day, 5 « days per week, and an afternoon
maintenance shift each day. Sixty-six persons were employed.
Hall Explosives, Inc., Hershey, Pennsylvania, was contracted to conduct blasting at
PenRoc. The principal operating official was Daniel Ray Leach, president/treasurer. Hall
Explosives employed a total of 28 persons, 4 of which were working at the mine on the
day of the accident. They subcontracted drilling to York Drilling Company, Inc., York,
Pennsylvania.
Limestone was mined by drilling and blasting multiple benches. Material was loaded by
a front-end loader into trucks and hauled to the aggregate plant where it was crushed,
screened, sized, washed and stockpiled. Depending upon stone quality, the principal uses
of the final products were road and specialty construction.
The last regular inspection of PenRoc was completed on October 15, 1996.
Physical Factors
The area where the accident occurred was located above Portal #1 of the abandoned
underground South Mine (see Appendix B). Portal #1 was reportedly filled to within a
few feet of the roof with mud and debris that had flowed in through joints and solution
cavities. A second entry (Portal #2) was located southwest of Portal #1 and was
separated from it by a pillar. The cap rock above Portal #1 was about 15 feet thick.
A shot had been set off just prior to the accident. The shot pattern was laid out in solid
ground, with the nearest blasthole approximately 10 feet north of Portal #1. A Beetle
drill was used to drill the blastholes. Prior to drilling, a level surface for operating the
drill was prepared by removing overburden down to the cap rock and filling voids in the
rock with 2RC stone. The highwall face, where the shot pattern was laid out, was
approximately 44 feet high.
Backbreak from the shot had brought down a section of the cap rock above the northeast
side of Portal #1 (identified in Appendix B, as area "A"). The section of cap rock
(identified in Appendix B as area "B"), that Kimmel is believed to have been standing on
when it collapsed, was above the southwest side of Portal #1, adjacent to the pillar
separating Portals #1 and #2. Kimmel fell about 15 feet with the section of cap rock and
was crushed and partially buried by the falling material.
Kimmel and Mark Proctor, senior blaster/sales representative, had examined the blast site
from the bottom of the highwall the day before the accident. They discussed the
possibility that the shot might bring down the section of the roof above the entry (Portal
#1). Kimmel had also mentioned this possibility to the mine operator. The area of cap
rock above Portal #1, however, had not been posted or barricaded to warn of the
potentially hazardous conditions.
Description of Accident
On the day of the accident, the blast crew consisting of Ronald Kimmel, Jr., (victim) and
Todd Zimmerman, junior blaster/truck driver, arrived at the mine at approximately
7:15 a.m. David Craft and Bryan Kachurka, truck drivers/laborers, had arrived shortly
before. They immediately began checking and measuring blasthole depth, pumping water
from wet holes, loading and stemming holes, and gathering empty bags. They completed
preparation and the shot was connected and fired at 11:04 a.m.
After the shot, Kimmel and Zimmerman made a post-blast examination from atop the
highwall. According to Zimmerman, it looked like proper detonation and no cracks or
"backbreak" were observed. Additionally, Kimmel had commented to him that the
section of roof (above Portal #1) that he and Proctor had been concerned about had come
down.
Following the post-blast examination of the top level, Zimmerman went to burn empty
bags, while Kimmel began retrieving lead-in lines near the edge of the highwall.
Christopher Colton, acting quarry manager, and John McGuire, stone plant lead man, had
arrived on the bench below to check the size and placement of the shot material. Both
men commented that they did not see anyone standing near the edge of the highwall when
they looked at it.
At approximately 11:10 a.m., Colton, McGuire, and Zimmerman stated they heard rocks
falling. Colton and McGuire said when they looked toward the highwall, they saw that a
section of it had collapsed. None of the three men saw Kimmel. Zimmerman climbed
down onto the shot rock, saw Kimmel's arm, and began to dig him out.
Kimmel was covered by mud and 2RC stone which had engulfed him as the ground he
was standing on collapsed. Bryan Kachurka, truck driver/laborer, aided in recovering
Kimmel, and both men administered CPR. While recovery was in progress, a call was
placed to 911, and a local rescue squad arrived at 11:28 a.m. Kimmel was pronounced
dead at the scene by the coroner. Kimmel died as a result of blunt force trauma caused
by the fall and/or material falling onto him.
Conclusion
The primary cause of the accident was the failure to correct hazardous ground conditions
prior to allowing work in the area. A contributing factor was the failure to conduct a
complete post-blast examination. An examination for hazardous ground conditions was
not conducted from the bench level below, and the 2RC stone placed to level the surface
prior to drilling may have obstructed the ability to detect cracks from the upper bench
level.
Recommendation
It is recommended, before mining is done above or near underground workings, that the
location of drifts and crosscuts be identified. Additionally, areas either above or in front
of such workings, which could pose a hazard to miners, should be posted or barricaded.
Violations Issued to Global Stone PenRoc Inc.
Order No. 4296113
Issued on December 17, 1996, under the provisions of Section
103(k) of the Mine Act.
On December 17, 1996, a contract blaster suffered fatal injuries when the ground on
which he was standing collapsed, causing him to fall and become engulfed by mud and
2RC stone. The accident site shall not be altered until the Mine Safety and Health
Administration's accident investigation is completed to protect personnel pending an
investigation by MSHA.
This order was terminated on April 9, 1997. The area above the mine entries has been
barricaded and no mining is being conducted. Before mining in this area, the operator
shall develop a mining method which safely addresses the hazardous ground conditions.
Violations Issued to Hall Explosives Inc.
Citation No. 7700422
Issued on January 7, 1997, under the provisions of Section
104(a) of the Mine Act for violation of 30 CFR 56.3200:
At this operation, on December 17, 1996, a contract blaster suffered fatal injuries when
the ground on which he was standing collapsed, causing him to fall and become engulfed
by mud and 2RC stone. The accident occurred after a shot, which had been detonated
earlier in the day. The victim was retrieving lead-in blasting line at the time of the
accident. Ground conditions that created the hazard were not corrected before other work
was done in the area.
This citation was terminated on April 9, 1997. Additional training for all blasters was
conducted on ground control measures to be taken at all quarry shots.
Citation No. 7700423
Issued on January 7, 1997, under the provisions of Section
104(a) of the Mine Act for violation of 30 CFR 56.3401:
At this operation, on December 17, 1996, a contract blaster suffered fatal injuries when
the ground on which he was standing collapsed, causing him to fall and become engulfed
by mud and 2RC stone. The victim was retrieving lead-in blasting line at the time of the
accident. It was determined during the accident investigation that a complete post-blast
examination for loose ground was not made prior to work commencing in the area.
This citation was terminated on April 9, 1997. Additional training for all blasters was
conducted on ground control measures to be taken at all quarry shots.
//s//Dennis A. Yesko
Supervisory Mine Safety and Health Inspector
//s//Edward F. Skvarch
Mine Safety and Health Inspector
Approved by: James R. Petrie, District Manager
Related Fatal Alert Bulletin: [FAB96M46]
|