|
|
A to Z Index |
Find It! in DOL |
[skip navigational links]
Search MSHA's Website
|
|
Printer Friendly Version (Contains All Graphics)
UNITED
STATES DEPARTMENT
OF LABOR MINE
SAFETY AND HEALTH ADMINISTRATION COAL
MINE SAFETY AND HEALTH REPORT
OF INVESTIGATION Shaft
Construction for Underground Mine Fatal Fall
of Persons Frontier-Kemper
Constructors Inc. (A01) at Gibson
Mine Gibson
|
|
Distance (Feet) |
#1 (Inches) |
#2 (Inches) |
#3 (Inches) |
Average (Inches) |
FKCI (Inches) |
|
0 |
1.375 |
1.374 |
1.377 |
1.375 |
1.375 |
|
100 |
1.378 |
1.378 |
1.378 |
1.378 |
1.375 |
|
200 |
1.363 |
1.363 |
1.362 |
1.363 |
1.365 |
|
300 |
1.369 |
1.369 |
1.370 |
1.369 |
1.370 |
|
400 |
1.368 |
1.371 |
1.369 |
1.369 |
1.370 |
|
500 |
1.375 |
1.377 |
1.375 |
1.376 |
1.375 |
4) HOIST ROPE SPEED TESTS: Tests were conducted to verify the speed of
the hoist rope under various conditions.
The hoist rope was marked (painted) in three 50-foot increments for a
total of 150 feet. The distance for each
increment and total distance traveled were timed with a stopwatch to the
nearest half second. Three tests were
conducted with the hoist operating at various speeds including the following:
Test 1 – The speed at which
personnel usually travel through the open doors.
Test 2 – The speed at which
personnel travel when they are within 100 feet of any stop.
Test 3 – The maximum speed at
which personnel are lowered.
During each of the tests the speed
indicated at the hoist operator’s station was recorded along with a timed test
of the rope. Each test was conducted
twice and the results are shown in Table 2.
Table 2.
Hoist Rope Speeds for Hoisting Personnel under various conditions.
|
|
0 – 50 feet |
50 – 100 feet |
100 – 150 feet |
0 – 150 feet |
Hoist House Speed |
|
Test 1
(a) |
55 FPM (55 sec) |
56 FPM (54 sec) |
57 FPM (53 sec) |
55 FPM (162
sec) |
20 FPM |
|
Test 1
(b) |
58 FPM (52 sec) |
59 FPM (51 sec) |
59 FPM (51 sec) |
58 FPM (154
sec) |
|
|
Test 2
(a) |
120 FPM (25 sec) |
136 FPM (22 sec) |
130 FPM (23 sec) |
129 FPM (70 sec) |
100 FPM |
|
Test 2
(b) |
130 FPM (23 sec) |
136 FPM (22 sec) |
136 FPM (23 sec) |
134 FPM (67 sec) |
|
|
Test 3
(a) |
333 FPM (9 sec) |
375 FPM (8 sec) |
400 FPM (7.5
sec) |
367 FPM (24.5
sec) |
380 FPM |
|
Test 3
(b) |
300 FPM (10 sec) |
375 FPM (8 sec) |
425 FPM (7 sec) |
360 FPM (25 sec) |
|
Additionally, the maximum
overspeed for lowering personnel in the shaft was verified. Three tests were conducted by lowering the
bucket into the shaft at the maximum speed for personnel. A tachometer was used to measure the rope
speed at the top of the shaft as the bucket was lowered. The tachometer measurements of the rope speed
at the top of the shaft ranged from 450 to 465 fpm when the overspeed
controller activated. The speed
indicator inside the hoist house for each of the tests was approximately 500
fpm.
5) EQUIPMENT AND CONSTRUCTION
MATERIALS: The sinking bucket was
typically used for lowering materials in the shaft. Items that could not be readily lifted or
easily put into the bucket were rigged beneath it. At the time of the accident, a 20-foot-long,
2-inch-wide nylon sling (SN 4230767) manufactured by Black Diamond Lifting
Products, Booneville, IN, was attached to the bottom of the bucket with a
shackle. The sling was rated for 11,000
pounds in a vertical hold, and 8,800 pounds in a choker hold position. A similar shackle, model S-209, manufactured
by The Crosby Group Incorporated, was attached through the eye of the sling and
allowed to hang freely from the bottom of the bucket when the sling was not
being used. This shackle had an overall
length of 6.56 inches and a nominal diameter of 1 inch.
6) SHACKLE POSITION IN COLLAR
DOORS: Based upon eyewitness accounts,
the shackle attached to the end of the 20-foot nylon sling (free end) was found
in one of the collar door horizontal beams immediately after the accident. Given the geometry of the shaft opening and
assuming the bucket is oriented in the center of this opening when entering the
shaft, a range of horizontal distances and swing angles necessary for the
shackle to become caught in the collar door structure was determined. The shackle would have to travel between 20 ⅝ and 68 ½ –inches with swing angles
between 4.9 and 16.5 degrees (from vertical) to come to rest in the collar door
structure. MSHA investigators used the
interview information and examined several positions of the shackle in the door
in an attempt to recreate a possible final position of the shackle. Three positions of the shackle were examined
in the collar doors. They are shown in Exhibits
4-6. For each of the shackle positions
examined, a force was applied to the sling in the up and down direction to
simulate the travel direction of the bucket.
Forces applied in the up and down direction to the sling as shown in
Position 1 (Exhibit 4) caused it to pull out of the beam. Forces applied in the down direction to the
sling shown in Position 2 (Exhibit 5) caused it to pull out of the beam, while
forces applied in the up direction caused the shackle to wedge itself into the
beam, causing the sling to tighten.
Forces applied in the up direction to the sling shown in Position 3
(Exhibit 6) caused it to pull out of the beam, while forces applied in the down
direction caused the shackle to wedge itself into the beam, causing the sling
to tighten. Based on these tests, it is consensus
of the accident investigation team that the sling was in Position 3, causing
the bucket to tip or overturn as it was lowered.
7) WEATHER AT THE TIME OF THE
ACCIDENT: According to the
SHAFT SINKING PLAN:
Frontier-Kemper’s Shaft Sinking
Plan, which was in effect at the time of the accident, was approved on
However, the use of fall
protection (belts) and the requirements for the transporting of supplies and
materials are mandated by 30 CFR Sections 77.1908(o) and 77.1908 (i),
respectively.
The approved shaft sinking plan,
issued to Frontier-Kemper rather than the mine operator, was reviewed by the
accident investigation team. Based upon
the circumstances and preliminary findings of the accident investigation, it
was determined that Frontier- Kemper’s plan should be revised to adequately
address the use of fall protection equipment and the transporting of supplies
and materials. In order to address the
investigators’ concerns and to prevent a similar occurrence, the District 8 Manager
requested the plan be revised.
Additional safety precautions were
added to the shaft sinking plan to further enhance the safety of the miners
throughout the shaft sinking operation and included the following:
·
All
persons shall use a suitable full harness and be tied off when riding in the
shaft sinking bucket.
·
When
entering and exiting the shaft sinking bucket at the work deck, all persons
shall be tied off. All persons must
remain tied off to the bucket until they are tied off to the deck.
·
Adequate
fall protection shall be in place or used when personnel are working on the
work deck, such as a third cable rail.
·
A
means shall be provided for safe footing when persons are embarking or
disembarking from the sinking bucket at the work deck, such as a chain securing
the bucket to the deck.
·
Permissible
wireless emergency communication devices shall be required between persons
riding the bucket, the hoistman and the toplander.
·
Straps,
lanyards or rigging shall not be attached to the bottom of the bucket when
transporting persons.
·
When
transporting personnel in the shaft, the toplander or other personnel will be
stationed at the collar, in communication with the hoistman and be able to
visually observe the bucket until it descends past the collar doors.
·
The
speed of the buckets transporting persons shall not exceed 500 feet per minute
and not more than 200 feet per minute when within 100 feet of any stop per
Title 30 Code of Federal regulations, Part 77, Subpart T, Section 1908,
Paragraph (j).
·
The
means for preventing these speeds shall be provided automatically by Lilly
controls or other similar means.
·
Training
shall be provided regarding these items and 5000-23 forms shall be completed
for the training.
These provisions were approved and made a part of the shaft
sinking plan on
FALL PROTECTION-ANSI STANDARDS
As previously stated, at the time
of the accident Frontier-Kemper’s approved plan did not address the use of full
body harness fall protection. Full body
harness protection is widely practiced throughout industry where fall hazards
of greater than four (4) feet are known to exist.
At the time of the accident,
standards of the American National Standards Institute (ANSI) and MSHA’s own
regulations, (30 C.F.R. Section 77.1710(g) and 77.1908(o)), did not
specifically address the use of full body harness fall protection in
these situations.
In October 2007, ANSI implemented
new standards that now provide guidelines for fall prevention. The ANSI Z359-2007 standard, which was not in
effect at the time of this accident, is designed to provide a proactive,
multi-faceted fall protection program with emphasis on training of both
supervisors and employees in work-at-heights activities. Design of the work site with fall prevention
in mind is recommended as well as personal fall arrest systems when the
work-at-heights distance exceeds four feet.
The accident investigation team
recommends that these standards be considered when formulating and evaluating
all future shaft and slope sinking plans.
MECHANISM OF THE ACCIDENT:
The use of the sling suspended
from the bottom edge of the bucket created a medium for the introduction of
external forces and, combined with the absence/non-use of properly attached
fall protection (belts), contributed to the fatal accident.
A number of safety belts, with
attached lanyards, piled near the shaft collar and among the detritus of used
medical supplies and rescue equipment, were found by the investigation
team,. However, at that time it could
not be positively determined to whom the belts were assigned or belonged, or if
they had been in use by the victims at the time of the accident. Interviews revealed that full body harness
fall protection, although available at the site, was not routinely used by
miners being transported in the bucket prior to the accident.
A review of MSHA training videos
available at the time of the accident showed persons being transported in
sinking buckets, with and without use of fall protection. However, the training videos did not show the
use of slings attached to the bucket while persons were being transported in
the bucket. These training materials
were recalled by MSHA following this accident.
MSHA standards clearly address the
use of ‘safety belts’ when persons are required to work in or over a shaft
where there is a drop of 10 or more feet.
Use of safety belts in this instance may have either prevented or
mitigated the severity of this accident.
Use of the described sling, in and
of itself, is not directly contrary to any standard. However, the presence of the unsecured sling
allowed for the loss of control of the bucket required by the standard found at
30 C.F.R. 1908-1. During interviews, it
was revealed that, prior to the accident, the sling and accompanying materials
and supplies, had been frequently attached to the sinking bucket while persons
were being transported in the bucket.
Due to the geometry and weight of
the sinking bucket, absent the exertion of external forces (sling), it is
highly improbable that the bucket could have sufficiently tipped or inverted, to
cause its contents to fall.
TRAINING OF THE VICTIMS:
Frontier-Kemper’s training records
were examined by representatives of MSHA’s Educational Field Services. The record
of experienced miner training and task training for Ashmore and the hazard
training record for
An analysis was conducted to identify the most basic causes
of the accident that were correctable through reasonable management
controls. During the analysis, root
causes were identified that, if eliminated, would have either prevented the accident
or mitigated its consequences. The
following root causes were identified as a result of the investigation. In each case, an effective management system,
procedure or policy was not in place to assure compliance with the regulation
or safe mining procedure.
Listed
below are root causes identified during the analysis and the respective
corrective actions implemented to prevent a recurrence of the accident:
Corrective Action:
The independent contractor’s approved shaft sinking plan has been
revised to include provisions that persons will not be transported with
anything attached to the bucket.
Corrective Action:
The independent contractor’s approved shaft sinking plan has been
revised to require the toplander or other personnel to be stationed at the
collar, in communication with the hoistman and be able to visually observe the
bucket until it descends past the collar doors.
Corrective Action:
The independent contractor’s approved shaft sinking plan has been
revised to include the use of fall protection when persons are transported in
the sinking bucket.
The accident
occurred as a result of Frontier-Kemper’s failure to ensure that the hoist was under the control of
the hoistman at all times when persons were in the shaft. The toplander was not at his station as the
bucket was being lowered through the shaft collar doors and the hoistman had no
visual contact with the bucket at this point.
The hoistman lost control of the bucket when the nylon sling and shackle
entangled with the shaft collar door.
The contractor also failed to ensure that adequate fall protection was
utilized while persons were transported in the sinking bucket.
1. A 103(k) Order, No.
7489388 was issued to ensure the safety of the miners until the
investigation could be completed.
2. A 104(a) Citation, No. 7502227,
was issued to Frontier-Kemper Constructors Inc. for a violation of 30 CFR 77.
1908 – 1, stating that the independent contractor failed to ensure that the
hoist was under the control of the hoistman when men were in the shaft.
During the course of the investigation of a multiple
fatality accident which occurred on
The independent contractor failed to assure that the hoist
was under the control of a hoistman at all times when men were in the
shaft. The sinking bucket from which
three victims fell to their deaths was not visible to the hoistman, due to
distances and structural obstructions between the hoistman’s operating station
and the shaft collar. In addition, the ‘toplander’, whose duties include
advising the hoistman of the positions of men and equipment, was not at his
station at the time of the accident.
Finally, control of the hoist was lost when a sling and shackle,
attached to the bottom of the sinking bucket, became entangled with the shaft
collar door, resulting in the sinking bucket tipping over and causing three
victims to fall to their deaths. In
addition to the three persons in the sinking bucket, five other men were
working at or near the shaft bottom at the time of the accident and were
exposed.
3. A 104(a) Citation, No. 7502228, was issued to
Frontier-Kemper Constructors Inc. for a violation of 30 CFR 77.1908(o) stating
that the Contractor allowed persons to ride the sinking bucket without proper
fall protection.
During the course of the investigation of a multiple
fatality accident which occurred on
The independent contractor failed to require the use of
properly attached fall protection when persons were riding the sinking
bucket. Three persons traveling in the
sinking bucket fell approximately 550 feet to their deaths after the bucket
inverted. None of the victims wore
properly attached fall protection.
List of Persons Participating in the Investigation
Frontier-Kemper Constructors, Inc.
George Zugel............... Corporate Safety Director
Kyle Wooten....................... Project Manager
Scott Harrell........ Corporate Human Resources
Director
R. Brian Hendrix......... Attorney, Patton-Boggs, LLP
Mark Savitt................ Attorney, Patton-Boggs, LLP
Henry Chajet............. Attorney, Patton-Boggs, LLP
H. John Head. Consulting Engineer, Continental Placer
Inc.
Gibson
Mike Stanley...................... General Manager
Don “Blink” McCorkle...... Deputy Commissioner
MSHA
Charles Grace...... Assistant District Manager,
District 7
Carl Boone............. Acting District Manager, District 8
David Whitcomb.. Assistant District Manager, District 8
Mike Rennie......... Supervisory C. M. S. & H., District 8
Ronald Stahlhut... Supervisory C. M. S. & H.,
District 8
Edward Ritchie Conference and Litigation Officer,
District 8
Bryan Sargeant Supervisory Special Investigator,
District 8
Bruce Harris............. Special Investigator,
District 8
Michael Kalich Mining Engineer, Headquarters Safety
Division
Jarrod Durig........... Civil Engineer, Technical
Support
Michael Snyder..... Mining Engineer, Technical Support
Leyland Payne......... Supervisory Training Specialist
Javier Romanach............. Office of the Solicitor
Kevin Doan................. Mining Engineer, District 7
|
|
www.msha.gov | www.dol.gov |
|
| ||
|---|---|---|
|
| ||
|
Mine Safety and Health Administration (MSHA) 1100 Wilson Boulevard, 21st Floor Arlington, VA 22209-3939 |
Phone:
(202) 693-9400 Fax-on-demand: (202) 693-9401 Technical (web) questions: Webmaster On-line Filing Help: MSHAhelpdesk@dol.gov or call (877) 778-6055 Contact Us | |