[Federal Register: December 29, 2004 (Volume 69, Number 249)] [Notices] [Page 78046-78047] ----------------------------------------------------------------------- DEPARTMENT OF LABOR Mine Safety and Health Administration Fee Adjustments for Testing, Evaluation, and Approval of Mining Products AGENCY: Mine Safety and Health Administration (MSHA), Labor. ACTION: Notice of fee adjustments. ----------------------------------------------------------------------- SUMMARY: This notice revises our [MSHA Approval and Certification Center (A&CC)] user fees. Fees compensate us for the costs that we incur for testing, evaluating, and approving certain products for use in underground mines. We based the 2005 fees on our actual expenses for fiscal year 2004. The fees reflect changes both in our approval processing operations and in our costs to process approval actions. DATES: This fee schedule is effective from January 1, 2005, through December 31, 2005. FOR FURTHER INFORMATION CONTACT: Steven J. Luzik, Chief, Approval and Certification Center (A&CC), 304-547-2029 or 304-547-0400. SUPPLEMENTARY INFORMATION: Background On May 8, 1987 (52 FR 17506), we published a final rule, 30 CFR part 5--Fees for Testing, Evaluation, and Approval of Mining Products. The rule established specific procedures for calculating, administering, and revising user fees. We have revised our fee schedule for 2004 in accordance with the procedures of that rule and include this new fee schedule below. For approval applications postmarked before January 1, 2005, we will continue to calculate fees under the previous (2004) fee schedule, published on December 30, 2003. Fee Computation In general, we computed the 2005 fees based on fiscal year 2004 data. We calculated a weighted-average, direct cost for all the services that we provided during fiscal year 2004 in the processing of requests for testing, evaluation, and approval of certain products for use in underground mines. From this cost, we calculated a single hourly rate to apply uniformly across all of the product approval categories during 2005. Dated: December 22, 2004. David G. Dye, Acting Assistant Secretary for Mine Safety and Health. FEE SCHEDULE EFFECTIVE JANUARY 1, 2005 (Based on FY 2004 data)
------------------------------------------------------------------------
HOURLY RATE
ACTION TITLE ($)
------------------------------------------------------------------------
Fees for Testing, Evaluation, and Approval of all Mining 66
Products \1\..............................................
Retesting for Approval as a Result of Post-Approval Product
Audit \2\.................................................
------------------------------------------------------------
30 CFR PART 15--EXPLOSIVES TESTING
------------------------------------------------------------------------
Permissibility Tests for Explosives:
Weigh-in............................................... 462
Physical Exam: First size.............................. 325
Chemical Analysis...................................... 1,977
Air Gap--Minimum Product Firing Temperature............ 460
Air Gap--Room Temperature.............................. 352
Pendulum Friction Test................................. 163
Detonation Rate........................................ 352
Gallery Test 7......................................... 7,436
Gallery Test 8......................................... 5,533
Toxic Gases (Large Chamber)............................ 805
Permissibility Tests for Sheathed Explosives:
Physical Examination................................... 128
Chemical Analysis...................................... 1,044
Gallery Test 9......................................... 1,944
Gallery Test 10........................................ 1,944
Gallery Test 11........................................ 1,944
Gallery Test 12........................................ 1,944
Drop Test.............................................. 648
Temperature Effects/Detonation......................... 672
Toxic Gases............................................ 580
------------------------------------------------------------------------
\2\ Fee based upon the approval schedule in effect at the time of retest. [FR Doc. 04-28452 Filed 12-28-04; 8:45 am] BILLING CODE 4510-43-P |
|
|
www.msha.gov | www.dol.gov |
|
| ||
|---|---|---|
|
| ||
|
Mine Safety and Health Administration (MSHA) 1100 Wilson Boulevard, 21st Floor Arlington, VA 22209-3939 |
Phone:
(202) 693-9400 Fax-on-demand: (202) 693-9401 Technical (web) questions: Webmaster On-line Filing Help: MSHAhelpdesk@dol.gov or call (877) 778-6055 Contact Us | |