Willow Creek Mine Fire - A Chronology of Events


MSHA - Willow Creek Fire Image
Click Picture for Enlargement


Week of December 13, 1998

Mine rescue teams re-entered the mine and successfully completed the recovery/re-ventilation phase to No. 9 Crosscut of the D Northeast Mains. The Main Fan was restarted during this period. Because of the significant methane/carbon dioxide liberation, a horizontal in-mine degasification system was installed to remove the gases from the sealed area. The vertical gob degasification system was also used. Monitoring locations were re-established farther in the mine.