Petition for Modification
In the matter of
Mingo Logan Coal Company
Mountaineer Alma-A Mine
I.D. No. 46-08730
Docket No. M-2001-050-C
30 CFR 75.1700
PROPOSED DECISION AND ORDER
On April 27, 2001, a petition was filed seeking a modification of the application of 30 CFR 75.1700 to Petitioner's Mountaineer Alma-A Mine, located in Mingo County, West Virginia.
May 17, 2001, MSHA conducted a meeting with the petitioner's mine officials. There was no designated miner's representative for the mine. During that meeting, the petitioners proposed alternative method was discussed and contrasted to more recent special terms and conditions being used in granting the requested modification. The petitioner's representatives indicated agreement with MSHA amending the alternative method to the most recent language.
The Petitioner alleges that the amended alternative method outlined in the petition as amended by MSHA will at all times guarantee no less than the same measure of protection afforded by the standard.
MSHA personnel conducted an investigation of the petition and filed a report of their findings and recommendations with the Administrator for Coal Mine Safety and Health. After a careful review of the entire record, including the petition and MSHA's investigative report and recommendation, this Proposed Decision and Order (PDO) is issued.
Finding of Fact and Conclusion of Law
The alternative method proposed by the Petitioner (as amended by the recommendations of MSHA) will at all times guarantee no less than the same measure of protection afforded the miners under 30 CFR 75.1700 .
The active gas wells will be plugged and the petitioner will use continuous miners and longwall shears to cut through the wells, in accordance with the terms and conditions of this PDO. Any
abandoned gas wells which were cleaned and plugged prior to issuance of this PDO will be individually evaluated to determine compliance with the terms and conditions described below prior to mining through, or whenever the safety barrier is reduced to a distance less than the District Manager would approve pursuant to Section 75.1700. Unless the existing records show that well to have been plugged using techniques equivalent to the amended alternative method and that information is submitted and accepted in accordance with Paragraph 2(s) as providing the required level of safety by the District Manager, the well shall be again cleaned, inadequate plugging materials drilled out and the well plugged in accordance with the terms and conditions of this proposed decision and order.
MSHA contacted The Mountaineer Alma-A Mine Safety Director, Rick Dillon, to clarify the intended utilization of the petitioner's proposed alternative method. He provided following information:
1. Alma-A Coal Seam is being mined. Seam is 40 to 50 inches in thickness. All mining is above drainage so the mine liberates little methane on seam. Therefore, no need for provision to leave portion of wellbore as degasification hole. He also indicated that the gas wells are already professionally plugged.
2. Alma-C seam present below the mine workings. That seam is 36 inches in thickness.
3. Lower Cedar Grove Coal Seam above is above the mine workings. That seam is 60 inches in thickness.
4. Interval for all three seams approximately 140 feet so total expansive cement interval would be 440 feet to meet the minimum requirement for plugging.
5. There are only 5 abandoned and plugged gas well to be cut through. First cut through needs to occur in August 2001. Only two cut throughs to be by longwall shear. Other 3 cut throughs by continuous miners.
6. Wells were commercial gas wells, each several thousand feet deep. However, excellent records on wells and well plugging are available and will be provided to MSHA District Manager or his representative.
The above information concerning the gas wells suggests that special attention to securing and interpreting the suite of drill logs required by Paragraph 1(a)(4) is needed to assure that at a minimum the expanding cement plug extends from at least 200 feet below the lowest minable seam through 100 feet above the highest minable seam, unless the seams are separated by an interval greater than 300 feet, in which case each seam may be plugged individually. The "suite of drill logs", referenced above, may include drillers logs, nearby core hole records, and mine maps but such records must be carefully evaluated for completeness and accuracy.
On the basis of the petition and the findings of MSHA's investigation, Mingo Logan Coal Company is granted a modification of the application of 30 CFR 75.1700 to its Mountaineer Alma-A Mine.
ORDER
Wherefore, pursuant to the authority delegated by the Secretary of Labor to the Administrator for Coal Mine Safety and Health, and pursuant to Section 101(c) of the Federal Mine Safety and Health Act of 1977, 30 U.S.C., sec. 811(c), it is ordered that Mingo Logan Coal Company's Petition for Modification of the application of 30 CFR 75.1700 in the Mountaineer Alma-A Mine is hereby:
GRANTED, for mining through or near (whenever the safety barrier diameter is reduced to a distance less than the District Manager would approve pursuant to Section 75.1700) plugged oil or gas wells penetrating the coal seam being mined and other minable coal seams using continuous miners, conventional mining or longwall mining methods, conditioned upon compliance with the following terms and conditions:
1. Procedures to be utilized when plugging oil or gas wells.
a. Cleaning out and preparing oil and gas wells. Prior to plugging an oil or gas well, the following procedure shall be followed:
(1) A diligent effort shall be made to clean the borehole to the original total depth. If this depth cannot be reached, the borehole shall be cleaned out to a depth which would permit the placement of at least 200 feet of expanding cement below the base of the lowest minable coal bed.
(2) When cleaning the borehole, a diligent effort shall be made to remove all the casing in the borehole. If it is not possible to remove all casing, the casing which remains shall be perforated, or ripped, at intervals spaced close enough to permit expanding cement slurry to infiltrate the annulus between the casing and the borehole wall for a distance of at least 200 feet below the base of the lowest minable coal bed.
(3) If the cleaned-out borehole produces gas, a mechanical bridge plug shall be placed in the borehole in a competent stratum at least 200 feet below the base of the lowest minable coal bed, but above the top of the uppermost hydrocarbon-producing stratum. If it is not possible to set a mechanical bridge plug, an appropriately sized packer or a substantial brush plug may be used in place of the mechanical bridge plug.
(4) A suite of logs shall be made consisting of a caliper survey, directional deviation survey, and log(s) suitable for determining the top and bottom of the minable coal beds and potential hydrocarbon producing strata and the location for the bridge plug.
(5) If the uppermost hydrocarbon-producing stratum is within 200 feet of the base of the lowest minable coal bed, properly placed mechanical bridge plugs or a suitable brush plug described in Subparagraph (a)(3) shall be used to isolate the hydrocarbon producing stratum from the expanding cement plug. Nevertheless, a minimum of 200 feet of expanding cement shall be placed below the lowest minable coalbed.
(6) The wellbore shall be completely filled and circulated with a gel that inhibits any flow of gas, supports the walls of the borehole, and increases the density of the expanding cement. This gel shall be pumped through open-end tubing run to a point approximately 20 feet above the bottom of the cleaned out area of the borehole or bridge plug.
b. Plugging oil or gas wells to the surface. The following procedures shall be utilized when plugging gas or oil wells to the surface:
(1) A cement plug shall be set in the wellbore by pumping an expanding cement slurry down the tubing to displace the gel and fill the borehole to the surface. (As an alternative, the cement slurry may be pumped down the tubing so that the borehole is filled with Portland cement or a Portland cement-fly ash mixture from a point approximately 100 feet above the top of the lowest minable coal bed to the surface with an expanding cement plug extending from at least 200 feet below the lowest minable coal bed to the bottom of the Portland cement.) There shall be at least 200 feet of expanding cement below the base of the lowest minable coal bed.
(2) A small quantity of steel turnings, or other small magnetic particles, shall be embedded in the top of the cement near the surface to serve as a permanent magnetic monument of the borehole.
c. Plugging oil or gas wells using the vent pipe method. The following procedures shall be utilized when using the vent pipe method for plugging oil and gas wells:
(1) A 4-½ or larger vent pipe shall be run into the wellbore to a depth of 100 feet below the lowest minable coal bed and swedged to a smaller diameter pipe, if desired, which will extend to a point approximately 20 feet above the bottom of the cleaned out area of the borehole or bridge plug.
(2) A cement plug shall be set in the wellbore by pumping an expanding cement slurry, Portland cement, or a Portland cement-fly ash mixture down the tubing to displace the gel so that the borehole is filled with cement. The borehole and the vent pipe shall be filled with expanding cement for a minimum of 200 feet below the base of the lowest minable coal bed. The top of the expanding cement shall extend upward to a point approximately 100 feet above the top of the highest minable coal bed.
(3) All fluid shall be evacuated from the vent pipe to facilitate testing for gases. During the evacuation of fluid, the expanding cement shall not be disturbed.
(4) The top of the vent pipe shall be protected to prevent liquids or solids from entering the wellbore, but permit ready access to the full internal diameter of the vent pipe when necessary.
2. The following cut-through procedures (a-t) apply whenever the petitioner reduces the safety barrier diameter to a distance less than the District Manager would approve pursuant to Section 75.1700 or proceeds with an intent to cut through a plugged well:
a. Prior to reducing the safety barrier to a distance less than the District Manager would approve pursuant to Section 75.1700 or proceeding with an intent to cut through a plugged well, the operator shall notify the District Manager or his designee.
b. A representative of the operator, a representative of the miners, the appropriate State agency, or the MSHA District Manager or designee may request that a conference be conducted prior to mining through any plugged well to review, evaluate, and accommodate any abnormal or unusual circumstance(s) related to the condition of the well or surrounding strata when such conditions are encountered. The party requesting the conference shall notify all other parties listed above within a reasonable time prior to the conference to provide opportunity for participation.
c. Mining through a plugged well shall be done on a shift approved by the District Manager or designee. The District Manager or designee and the miners' representative shall be notified by the operator in sufficient time prior to the mining-through operation in order to provide an opportunity to have representatives present.
d. When using continuous mining methods, drivage sights shall be installed at the last open crosscut near the place to be mined to ensure intersection of the well. The drivage sites shall not be more than 50 feet from the well. When using longwall mining methods, drivage sights shall be installed on 10-foot centers for a distance of 50 feet in advance of the well bore. The drivage sights shall be installed in the headgate and tailgate.
e. Firefighting equipment shall include fire extinguishers, rock dust, and sufficient fire hose to reach the working face area of the mining through when either the conventional or continuous mining method is used. The fire hose shall be located in the last open crosscut of the entry or room. When the longwall mining method is implemented, the fire hose shall be extended to the face area of the mine through. All fire hoses shall be ready for operation during the mining through.
f. Sufficient supplies of roof support and ventilation materials shall be available and located at the last open crosscut. In addition, an emergency plug and/or plugs shall be available in the immediate area of the mine through.
g. The quantity of air required by the approved mine ventilation plan, but not less than 9000 cubic feet per minute (cfm) of air, shall be used to ventilate the working face during the mining through operation using continuous mining or conventional mining methods. The quantity of air required by the ventilation plan, but not less than 30,000 cfm, shall reach the working face of a longwall during the mining through operation.
h. Equipment shall be checked for permissibility and serviced on the shift prior to mining through the well.
i. The methane monitor(s) on the longwall, continuous mining machine, or cutting machine and loading machine shall be calibrated on the shift prior to mining through the well.
j. When mining is in progress, tests for methane shall be made with a hand-held methane detector at least every 10 minutes from the time that mining with the continuous mining machine is within 30 feet of the well until the well is intersected and immediately prior to mining through. When mining with longwall mining equipment, the tests for methane shall be made at least every 10 minutes when the longwall face is within 10 feet of the well. During the actual cutting through process, no individual shall be allowed on the return side until mining through has been completed and the area has been examined and declared safe.
k. When using continuous or conventional mining methods, the working place shall be free from accumulations of coal dust and coal spillages, and rock dust shall be placed on the roof, rib and floor to within 20 feet of the face when mining through the well. On longwall sections, rock dusting shall be conducted and placed on the roof, rib and floor up to both the headgate and tailgate.
l. When the wellbore is intersected, all equipment shall be deenergized and the place thoroughly examined and determined safe before mining is resumed. Any well casing shall be removed and no open flame shall be permitted in the area until adequate ventilation has been established around the wellbore.
m. After a well has been intersected and the working place determined safe, mining shall continue inby the well a sufficient distance to permit adequate ventilation around the area of the wellbore.
n. No person shall be permitted in the area of the mining through operation except those actually engaged in the operation, company personnel, representatives of the miners, personnel from MSHA, and personnel from the appropriate State agency.
o. The mining through operation shall be under the direct supervision of a certified official. Instructions concerning the mining through operation shall be issued only by the certified official in charge.
p. MSHA personnel may interrupt or halt the mining through operation when it is necessary for the safety of the miners.
q. A copy of this PDO shall be maintained at the mine and be available to the miners.
r. The Petitioner shall file a plugging affidavit setting forth the persons who participated in the work, a description of the plugging work, and a certification by the Petitioner that the well has been plugged as described.
s. Within 60 days after this PDO becomes final, the Petitioner shall submit proposed revisions for its approved 30 CFR Part 48 training plan to the Coal Mine Safety and Health District Manager. These proposed revisions shall include initial and refresher training regarding compliance with the terms and conditions stated in the PDO.
Any party to this action desiring a hearing on this matter must file in accordance with 30 CFR 44.14, within 30 days. The request for hearing must be filed with the Administrator for Coal Mine Safety and Health, 4015 Wilson Boulevard, Arlington, Virginia 22203.
If a hearing is requested, the request shall contain a concise summary of position on the issues of fact or law desired to be raised by the party requesting the hearing, including specific objections to the proposed decision. A party other than Petitioner who has requested a hearing shall also comment upon all issues of fact or law presented in the petition, and any party to this action requesting a hearing may indicate a desired hearing site. If no request for a hearing is filed within 30 days after service thereof, the Decision and Order will become final and must be posted by the operator on the mine bulletin board at the mine.
____________________________________________
Michael J. Lawless
Deputy Administrator
for Coal Mine Safety and Health