Petition - Docket No. 2003-099-C

In the matter of                                Petition for Modification

River Hill Coal Company, Inc.

River Hill Coal Company Mine

I.D. No. 36-00884           Docket No. M-2003-099-C

PROPOSED ORDER OF DISMISSAL

On January 14, 2004, a petition was filed by River Hill Coal Company, Inc., seeking a modification of the application of 30 CFR 77.700-1(c) to the Petitioner's River Hill Coal Company Mine, located in Clearfield County, Pennsylvania. The Petitioner alleged that the alternate method proposed in the petition would at all times provide the same degree of safety as the existing standard. On September 3, 2004, MSHA received notification from the mine operator requesting that the petition for modification be withdrawn since modification of the application of the standard is not necessary.

Wherefore, pursuant to the authority delegated by the Secretary of Labor to the Administrator for Coal Mine Safety and Health, and pursuant to Section 101(c) of the Federal Mine Safety and Health Act of 1977, 30 U.S.C., Sec. 811(c), it is ordered that River Hill Coal Company, Inc.’s Petition for Modification of the application of 30 CFR 77.700-1(c) in the River Hill Coal Company Mine is hereby:

DISMISSED without prejudice.

Any party to this action desiring a hearing on this matter must file in accordance with 30 CFR 44.14, within 30 days. The request for hearing must be filed with the Administrator for Coal Mine Safety and Health, 1100 Wilson Boulevard, Arlington, Virginia 22209-3939.

If a hearing is requested, the request shall contain a concise summary of position on the issues of fact or law desired to be raised by the party requesting the hearing, including specific objections to the proposed decision. A party other than Petitioner who has requested a hearing shall also comment upon all issues of fact or law presented in the petition, and any party to this action requesting a hearing may indicate a desired hearing site.

If no request for a hearing is filed within 30 days after service thereof, the Decision and Order will become final and must be posted by the operator on the mine bulletin board at the mine.

 

 

Terry L. Bentley

Chief, Division of Safety

Coal Mine Safety and Health