Skip to main content
U.S. flag

An official website of the United States government.

Final Report - Fatality #18 - December 16, 2009

Accident Report: Fatality Reference

CAI-2009-18

UNITED STATES

DEPARTMENT OF LABOR

MINE SAFETY AND HEALTH ADMINISTRATION 



COAL MINE SAFETY AND HEALTH 



REPORT OF INVESTIGATION 



Underground Coal Mine 



Fatal Fall of Roof Accident

December 16, 2009 



Sapphire Coal Company

Sandlick II Mine

Sandlick, Letcher County, Kentucky

I.D. No. 15-18782 



Accident Investigator 



Darrell E Hurley

Roof Control Specialist 



Originating Office

Mine Safety and Health Administration

District 6

100 Fae Ramsey Lane

Pikeville, KY 41501

Norman G. Page, District Manager



 


 

OVERVIEW



At approximately 8:40 p.m., on Wednesday, December 16, 2009, Phillip Newton, a 34-year old continuous mining machine operator for Sapphire Coal Company, received fatal injuries when a piece of rock measuring 13 feet long by 6 feet wide by 12 to16 inches thick fell from the roof and trapped Newton (victim) beneath it. The victim was cutting the No. 5 Right crosscut into the No. 6 entry (see Sketch of Accident Scene). 



The accident occurred because the operator failed to follow the approved roof control plan. Adverse roof conditions were present. Instead of following the plan and reducing the mining cut depth to 20 feet or less, the cut depth was increased to 49 feet. This was 9 feet longer than the maximum cut depth in the plan. 

 

GENERAL INFORMATION



Sapphire Coal Company, Sandlick II, is an underground bituminous coal mine located at Sandlick, Letcher County, Kentucky. The parent company is Metinvest B V. The principal officers of Sapphire Coal Company are John Schroeder, President, and Everett Kelly, Superintendent. The mine operates two nine-hour shifts per day, 5 days per week and employs 51 persons. The mine produces approximately 1,267 tons of coal per day. 



The last regular safety and health inspection (E01) of the mine prior to the accident was completed on September 30, 2009. The Non-Fatal Days Lost (NFDL) injury incidence rate at this mine prior to the accident was 0.00 compared to a national NFDL rate of 4.16. 



 

DESCRIPTION OF ACCIDENT



On Wednesday, December 16, 2009, the second shift began at 3:15 p.m. Israel Clark, Section Foreman, was instructed by Lee Roy Combs, Day Shift General Mine Foreman, to mine the crosscuts only, except the No. 2 and No. 3 entries could be mined for a distance of one cut each. The 12 man crew traveled underground to the working section and relieved the day shift crew on the section. This section had two continuous mining machines that alternated operation during the shift. A cut is taken on the left side of the section and when completed, the continuous mining machine on the right side of the section takes a cut. Second shift mining began on the left side of the section in the No. 3 entry. The first cut on the right side was the No. 6 Right crosscut, where one cut had previously been mined. The victim was operating the right side continuous mining machine. This cut went through into the No. 7 entry. After cutting through, the right side mining machine was moved to the last open crosscut in order to be serviced. Danny Morales, Electrician, helped Newton clean the demister on the wet bed scrubber. Newton asked Clark if they could cut the headings and Clark informed Newton he was instructed by Combs earlier to cut crosscuts only, except for the No. 2 and No. 3 entries, where they could take one cut. The right side mining machine was set up to start the No. 5 Right crosscut by around 7:00 pm. Clark traveled to No. 5 Right crosscut to get the mid-shift report on footage mined. Newton informed Clark he had mined approximately 30 feet on the right side and 25 feet on the left side of the current cut. Newton stated he had been having trouble mining this cut because it was rolling and dipping toward the right side of the crosscut. After Clark left, Newton continued mining the cut. 



Kenny Crase, Ram Car Operator had backed up to let Newton reposition his continuous mining machine from the left side to the right side. Crase could not see Newton from his position, but he saw a metal strap pull down from the roof and a small piece of rock fall. He then heard the pump motor on the continuous mining machine shut off. Crase called out for Newton, but did not receive a response and exited his ram car. Crase walked up and observed rock on the continuous mining machine, and rock lying where Newton should have been located. Crase called out for someone to help Newton. 



Danny Morales, French Holbrook, Johnnie Sandlin and Larry Stamper were located at the emergency sled when they heard the rock fall. They traveled up the No. 6 entry where Morales saw the rock on the front of the continuous mining machine. Sandlin went to inform Clark that the No. 5 Right crosscut had fallen in and they could not find Newton. Morales, Holbrook, and Stamper then traveled back around the coal pillar to the No. Five Right crosscut and saw what appeared to be Newton's hard hat under the rock. 



Clark traveled to the emergency telephone where he called Doug Benton, Second Shift Mine Foreman. He informed Benton of the fall at No. 5 Right crosscut and that no one could locate Newton. Benton said he would travel to the section. Clark traveled back to the accident location. Holbrook went to the emergency sled, where he loaded timbers and wooden crib blocks into the scoop bucket in order to secure the accident scene and perform recovery. The crew started setting timbers around the edge of the fall. Holbrook operated the scoop with its bucket to raise the rock. Newton was observed under the rock. Benton arrived and shortly thereafter, Ed Banks, Company Safety Inspector and Mike Eldridge, Inspector for the Kentucky Office of Mine Safety and Licensing, arrived. The rock was raised and supported with wooden crib blocks. Newton was moved to the first outby crosscut between No. 5 entry and No. 4 entry. Newton had no vital signs and he was placed on a backboard and transported to the surface. 



When Newton arrived on the surface he was examined by Wallace Bolling Jr., Letcher County Corner, and pronounced dead at 11:45 p.m. 

 

INVESTIGATION OF ACCIDENT



The MSHA Call Center was notified of the accident at 8:55 p.m. Coal Mine Safety and Health Supervisor, James Hager telephoned Sapphire Coal Company, Sandlick II Mine and issued a 103(j) Order verbally to Ed Banks, Safety Inspector. MSHA personnel were immediately dispatched to the scene and the 103(j) Order was formally issued in writing and modified to a 103(k) Order to ensure the safety of all persons at the mine. The investigation was conducted in cooperation with the Kentucky Office of Mine Safety and Licensing (KYOMSL). 



Photographs and relevant measurements were taken of the accident scene. A review of the training records was conducted. Interviews were conducted with 20 employees of Sapphire Coal Company. The interviews were conducted at the MSHA Whitesburg Field Office on December 18, 21, 22, 2009, and January 25, 2010. 

 

DISCUSSION



Section Development



The Four East Panel had been developed on 60 foot minimum entry centers and 75 foot minimum crosscut centers in accordance with the approved roof control plan (see Appendix A). 



It was decided by the mine superintendent and mine management to mine rooms off the right side of the Four East panel for a distance of approximately four crosscuts and then pillar the area without changing the orientation of the coal pillars. The mine engineering department, safety department, and the operation president were consulted and agreed with the change. Maps with the revised projections were printed and posted at the mine. The rooms to be driven on retreat of Four East panel were projected to be 75 feet entry centers and 60 feet crosscut centers. The approved roof control plan required a minimum of 60 feet entry centers. The orientation of the blocks caused the entry centers to be 75 feet making the width of the block along the crosscut to be 55 feet instead of 40 feet. The miners were accustomed to cutting the 40 feet wide block through in two cuts. When a turn-in is made, three cuts are required to cut through the 55 feet wide blocks in order to comply with the approved roof control plan. 



Roof Control



The approved roof control plan, dated March 4, 2009, specified that a minimum of a five foot long, fully grouted resin roof bolt be installed on four foot centers for primary roof support. 



Supplemental roof support of four, eight foot cable bolts to be installed in the intersections was required for areas to be second mined (pillared). The rooms which were being developed off Four East panel at the accident location were developed by the operator with the intention to be pillared. 



The minimum entry centers for mining rooms were 60 feet and the minimum crosscut centers for rooms was 75 feet. 



The maximum allowed extended cut depth was 40 feet. When subnormal or adverse conditions were encountered, the depth of the cut was required to be reduced to 20 feet or less. The safety precautions for mining an extended cut required the continuous mining machine operator to not expose any portion of his body inby the second row of undisturbed permanent supports. 



The Five Right crosscut where the accident occurred had the first cut (turn-in) mined on the day shift and was supported with five foot, 5/8 inch diameter resin grouted bolts. Metal roof straps had been installed perpendicular to the entry on four rows of roof bolts in the turn in and on three rows of roof bolts in the intersection before the crosscut was started. The metal straps were installed to provide supplemental roof support due to the presence of a sandy slicken-side that created a weak plane in the roof. The installation of metal straps was evidence of the roof bolting machine operators recognizing that the slicken-side area was an adverse roof condition. The crosscut was elevated slightly uphill and dipped downward to the right side. At mid-shift, Newton informed Clark that he had been having trouble with the cut being mined because the crosscut was dipping to the right side. The dip of the seam caused the continuous mining machine to drift to the right, rounding the crosscut back into the pillar block. It also caused the roof to be cut unevenly, with the left side being cut upward into the slicken-side plane at the left rib line. The cut depth was not reduced to 20 feet or less when adverse roof conditions were encountered, as required in the approved roof control plan. 



Excessive Cut Depth



The cut depth from the last row of primary support in the No. 5 Right crosscut to the first row of roof bolts in the No. six entry was measured to be approximately 49 feet. The maximum cut depth allowed by the approved roof control plan was 40 feet. 



Position of the Continuous Mining Machine Operator



Newton's body was located under the fallen rock between the first and second row of roof bolts. Two roof bolts in the first row were broken and portions were in the rock which had fallen. A visual warning device was hanging on the roof bolt furthest outby, which was in the second row of installed roof bolts from the newly mined, unsupported area. 



Examination



Three metal straps had been installed in the No. 5 entry when the entry was developed. When the turn-in for the No. 5 Right crosscut was bolted, four roof straps were installed perpendicular to the crosscut. One was installed at the slicken-sided fault. The second shift foreman traveled to this location before the continuous mining machine was positioned into the place and again at mid-shift report time. Newton had cut 30 feet on the right side and 25 feet on the left side. The second shift foreman did not identify the adverse roof conditions and did not instruct the continuous mining machine operator to reduce the cut depth because of the adverse conditions. 



Training



Training records were checked and found to be up to date for all employees. 

 

ROOT CAUSE ANALYSIS



An analysis was conducted to determine the most basic causes of the accident. Listed below are the root causes identified during the analysis and the corresponding corrective actions implemented to prevent a recurrence of the accident. 



Root Cause: Administrative controls, policies, and procedures were not utilized by the operator to ensure compliance with the approved roof control plan when it changed the orientation of the coal pillars that were going to be mined without prior MSHA approval. 



Corrective Action: The operator has discontinued mining the rooms off 4 East panel where the block orientation had been reversed. 



Root Cause: The operator did not reduce the cut depth to 20 feet or less where an adverse roof condition in the form of a sandy, slicken-side area was present. The approved roof control plan required the cut depth to be reduced to 20 feet or less where adverse or subnormal roof conditions were encountered. 



Corrective Actions: The approved roof control plan has been revised to specify a maximum of 20 feet cut depth in crosscuts and 30 feet cut depth in entries. The miners and management have been re-trained in the revised roof control plan to reduce cut depth under adverse roof conditions. 



Root Cause: An extended cut was mined in excess of the approved 40 feet. The cut depth measured approximately 49 feet. 



Corrective Actions: The operator has retrained the miners in the revised maximum cut depth allowed by the approved roof control plan. The maximum cut depth was reduced to 30 feet in entries and maximum of 20 feet in crosscuts. All persons were trained in the revised roof control plan and a depth indication mark was provided on the continuous mining machine for reference. Also, a letter from the mine President has been posted on the mine bulletin board, stating that all miners are to follow the approved roof control plan at all times. 



Root Cause: The continuous mining machine operator was not positioned outby the second row of undisturbed roof support while mining an extended cut. The machine operator was located between the first and second row of installed permanent support while mining an extended cut. 



Corrective Actions: All persons were retrained in the requirements of the approved roof control plan. The safety precautions were reviewed for mining extended cuts, including the safe location of the continuous mining machine operator. 



Root Cause: An inadequate on shift examination was conducted by the section foreman. Adverse roof conditions in the form of a sandy, slicken-side area existed in the area and had been supported with metal straps during the previous shift. The foreman was in the area where the accident occurred twice during the shift. The installation of straps in the area, the conversation with the mining machine operator having difficulty mining this cut, and the foreman's visual observations should have resulted in the foreman directing Newton to reduce the cut depth. 



Corrective Actions: The operator has trained their supervisory personnel to examine the mine roof for adverse geological conditions and to reduce the cut depth when adverse roof conditions are present. 

 

CONCLUSION



The accident occurred because the operator did not take the necessary steps to prevent these conditions: The rooms that were driven on the right side of Four East Panel on retreat were not oriented on 60 foot minimum entry centers and 75 foot minimum crosscut centers, as required in the approved roof control plan. Adverse roof conditions were present in the No. 5 Right crosscut and the cut depth was not reduced to 20 feet or less, as required in the approved roof control plan. The cut depth taken was in excess of 40 feet, the maximum allowed by the approved roof control plan. The continuous mining machine operator was not positioned outby the second row of permanent roof bolts being used for primary support while mining an extended cut. 

 

ENFORCEMENT ACTIONS



1. A 103 (j) Order, No. 6661224 was issued on December 16, 2009, to Sapphire Coal Company to assure the safety of all persons at the mine. The order was modified later to a 103(k) Order 



Condition or Practice: "This mine has experienced a roof fall accident at the mine on the MMU 001 section. This order is issued to assure the safety of any person at the coal mine until an examination or investigation is made to determine the mine is safe. Only those persons selected from company officials, state officials, the miners' representative and other persons who are deemed by MSHA to have information relevant to the investigation may remain in the affected areas." 



2. A 104(d) (1) Order, No. 8218166 was issued for a violation of 30 CFR § 75.220 (a) (1) for failure to comply with the approved roof control plan. 



Condition or Practice: The approved roof control plan was not being complied with on MMU 001. Pillaring had stopped in the Four East panel to develop rooms to the right. The approved roof control plan, dated March 4, 2009, required that only a minimum 60 foot entry centers and a minimum 75 foot crosscut centers be used in all phases of mining. The operator engaged in aggravated conduct, constituting more than ordinary negligence, by developing these rooms on 75 foot entry centers and 60 foot crosscut centers. The orientation of these blocks violated the minimum crosscut centers. This caused the crosscut centers to be less than the minimum 75 feet allowed in the approved roof control plan. This also caused the distance through the crosscut to change from 40 feet to 55 feet, causing deeper cuts to be taken to complete the cuts through. It normally took two cuts to put the crosscuts through on 60 foot centers and they were mining the 75 foot crosscuts centers through with two cuts. This violation is an unwarrantable failure to comply with a mandatory standard. 



3. A 104(d) (1) Order, No.8218167 was issued for a violation of 30 CFR § 75.220 (a) (1) for failure to comply with the approved roof control plan. 



Condition or Practice: The approved roof control plan was not being complied with on the MMU 001. The operator engaged in aggravated conduct, constituting more than ordinary negligence, by mining the right crosscut developed off the No. 5 entry through into the No. 6 entry for a distance of approximately 49 feet from the last row of installed roof bolts in the No. 5 Right crosscut, to the first row of installed roof bolts from the rib line of the No. 6 entry. When conducting a cut through, the cut depth is measured as the distance from the last row of installed permanent roof supports in the crosscut to the point that the roof is permanently supported by installed permanent roof support in the entry being cut in to. The approved plan allowed a maximum extended cut distance of 40 feet. This violation is an unwarrantable failure to comply with a mandatory standard. 



4. A 104(d) (1) Order, No. 8218168 was issued for a violation of 30 CFR § 75.220 (a) (1) for failing to comply with the approved roof control plan. 



Condition or Practice: The approved roof control plan was not being complied with on the MMU 001. Page 16, item 14 stated, "when subnormal or adverse roof conditions are encountered, the cut depth will be limited to 20 feet or less." Subnormal or adverse conditions had been encountered and roof straps had been installed on the day shift on the last four rows of roof bolts used for primary support. The foreman was in the area during the cut and discussed the conditions with the mining machine operator. He engaged in aggravated conduct by failing to direct the operator to reduce the cut depth to 20 feet or less. This violation is an unwarrantable failure to comply with a mandatory standard. 



5. A 104(a) Citation, No. 8218169 was issued for a violation of 30 CFR § 75.220 (a) (1) for failure to comply with the approved roof control plan. 



Condition or Practice: The continuous mining machine operator had cut Five Right crosscut into No. six entry while taking an extended cut and positioned himself between the first and second row of permanent roof support. The approved roof control plan stated on page 15, Item 3 that "the continuous mining machine operator and other persons in the area shall not expose any portion of their body inby the second row of undisturbed permanent roof supports." 



6. A 104(d) (1) Order, No. 8218170 was issued for a violation of 30 CFR § 75.362 (a) (1) for an inadequate workplace examination being conducted on the MMU 001. 



Condition or Practice: An inadequate on shift examination of the No. 5 entry, leading toward the No. six entry, was conducted by the evening shift foreman on December 16, 2009. The foreman traveled to the No. 5 Right crosscut while the mining machine operator was making the cut and the machine operator discussed with the foreman that he had been having trouble with the cut. Metal roof straps had been installed on the day shift this day and were present before the continuous mining machine started the cut. The foreman engaged in aggravated conduct by failing to identify the hazard and instruct the continuous miner operator to reduce the cut depth or move out of the area. This violation is an unwarrantable failure to comply with a mandatory standard. 



 




 

APPENDIX B





List of Persons Interviewed 



Sapphire Coal Company

James Everett Kelly ............... Superintendent

G. Fred Webb ............... Chief Engineer

Andy L. Fields ............... Manager of Safety & Human Resources

Travis F. Webb ............... Mine Engineer

Doug Benton ............... Second Shift General Mine Foreman

Hal Woody Adams ............... Day Shift Section Foreman

Israel Clark ............... Section Shift Section Foreman

Christopher Sturgill ............... Roof Bolter Operator

Daniel Baker ............... Mining Machine Operator

French P. Holbrook ............... Scoop Operator

Charles D. Stallard ............... Roof Bolt Operator

Bill E Holbrook ............... Roof Bolt Operator

Robbie Collins ............... Ram Car Operator

Kenny W. Crase ............... Ram Car Operator

Matthew R. Mullins ............... Ram Car Operator

Daniel Morales ............... Section Electrician / MET

Ricky G. Adams ............... Roof Bolt Operator

Sean Hall ............... Mining Machine Operator

Larry Stamper ............... Roof Bolt Operator

Johnnie Sandlin ............... Roof Bolt Operator

Lee Roy Combs ............... Day Shift Mine Foreman

APPENDIX C





List of Persons Participating in the Investigation 



Kentucky Office of Mine Safety and Licensing

David Mullins ............... Hazard District Supervisor 

Tracy Stumbo ............... Chief Accident Investigator

Tim Fugate ............... Accident Investigator

Michael Eldridge ............... Roof Control Inspector

Bob Banks ............... Inspector Principal

Daniel Bentley ............... Underground Safety Analyst

Mine Safety and Health Administration

David Ison ............... Supervisory Coal Mine Inspector

Darrell Hurley ............... Roof Control Specialist / Accident Investigator

David Steffey ............... Mining Engineer/Accident Investigator

Kenneth Fleming ............... Coal Mine Inspector/Accident Investigator 

Robert Bellamy ............... Staff Assistant/Accident Investigation Coordinator

Chris Barber ............... Attorney

James Newman ............... Coal Mine Inspector/Accident Investigator

Donny Young ............... Roof Control Specialist

George Mann ............... Roof Control Specialist

Jeffrey Miles ............... Roof Control Specialist

Jerry Bellamy ............... Mine Engineer/ Ventilation Specialist

Greg Hall ............... Civil Engineer