Skip to main content
U.S. flag

An official website of the United States government.

Final Report - Fatality #2 - February 20, 2015

Accident Report: Fatality Reference

CAI-2015-02

UNITED STATES

DEPARTMENT OF LABOR

MINE SAFETY AND HEALTH ADMINISTRATION 
 

COAL MINE SAFETY AND HEALTH 
 

REPORT OF INVESTIGATION 
 

Underground Coal Mine 
 

Fatal Roof Fall Accident

February 20, 2015

Heilwood Mine

Rosebud Mining Company, Inc.
Heilwood, Indiana County, Pennsylvania

I.D. Number 36-09407  
 

Accident Investigators 
 

Kerry J. Miller
Coal Mine Safety and Health Inspector/Roof Control Specialist 

 

John C. Burda

Coal Mine Safety and Health Inspector/Roof Control Specialist
 

James C. Miller

Coal Mine Safety and Health Inspector

Michael Gauna

Mining Engineer

Approval and Certification Center

Originating Office

Mine Safety and Health Administration

District 2

Paladin Professional Building

631 Excel Drive, Suite 100

Mount Pleasant, Pennsylvania 15666

Thomas E. Light, District Manager

 


OVERVIEW

On Friday, February 20, 2015, at approximately 2:05 p.m., Todd Trimble (victim), a 29-year-old roof bolter helper with 3 years and 11 months of total mining experience, was fatally injured when he was struck by a large section of roof rock.  Trimble was between the last full row of permanently installed roof bolts and the automated temporary roof support (ATRS), installing wire roof screen in the number 2 slope entry of A Mains.  The large roof rock fell between the last row of permanent supports and the ATRS, pinning the victim against the drill head canopy, causing fatal crushing injuries.  The roof rock measured 0.25 to 1.3 feet in thickness, 3 feet in width, and 11.5 feet in length.  Trimble was preparing to install permanent supports when he was struck by the rock.

 

GENERAL INFORMATION

The Heilwood Mine is an underground coal mine operating in the Lower Kittanning seam, located at Heilwood, Indiana County, Pennsylvania.  The mine is operated by Rosebud Mining Company.  Bituminous coal is mined at this operation with the room and pillar method of mining, utilizing one section.  The mine operator was developing three slope headings from the Lower Kittanning Seam (B Seam) to the Brookville seam (A Seam).  The mine operates two nine-hour production shifts and one maintenance shift, five to six days a week.  The mine employs 40 people with 35 working underground and 5 on the surface.  The average production, while mining the Lower Kittanning seam, was 625 tons of raw coal per day.

 

The principal officers for the mine at the time of the accident were:

 

            J. Clifford Forrest………………………………………………… President
David S. Doney……………………………………. General Mine Manager

            Scott Troutman…………………………………………….. Superintendent
Barry Houser………………………………………………... Mine Foreman
Stanley Popich……………………………… Manager of Safety and Health

The Mine Safety and Health Administration (MSHA) completed a regular safety and health inspection (E01) at this min on February 18, 2015. The Non-Fatal Days Lost (NFDL) injury incidence rate for this mine during the period of January through December 2014 was 3.10, compared to a national rate of 3.28 for this type of mine.

 

DESCRIPTION OF THE ACCIDENT

On Friday February 20, 2015, the daylight shift crew for the A Mains Section (MMU 001-0) travelled underground at 6:00 a.m in a diesel-powered mantrip to the section.  The section crew arrived on the A Mains Section at approximately 6:30 a.m.  After they arrived, Jeremy Mumau, Section Foreman, conducted an onshift examination of the faces and the rest of the crew conducted pre-operational examinations of the mining equipment.  Arron Mumau and Trimble were the normal operators for the roof bolting machine on the A Mains Section.

The roof bolting machine was located in the face area of the number 3 entry, which was not fully bolted when they arrived on the section (see Appendix A).  After performing the pre-operational examination, A. Mumau and Trimble finished bolting the number 3 entry.  The continuous mining machine operator, Jim Frantz, mined 10 feet in the number 4 entry, and then trammed the mining machine into the number 2 entry.  A. Mumau and Trimble trammed the roof bolting machine from the number 3 entry to the number 4 entry.  They began installing roof bolts in the number 4 entry while Frantz mined 10 feet from the face of number 2 entry.
Frantz finished mining in number 2 entry and trammed the mining machine into the number 3 entry to trim bottom to build and install bridges.  A. Mumau and Trimble finished bolting the number 4 entry and trammed the roof bolting machine from the number 4 entry into the number 2 entry (see Appendix B).

In the number 2 entry, A. Mumau and Trimble installed one row of roof bolts as the primary roof supports and one row of cable bolts as supplemental roof supports.  There was approximately 10 feet between the last full row of bolts and the face in the number 2 entry.  A. Mumau trammed the roof bolting machine inby and positioned the ATRS with the inby edge of the ATRS pads 5 feet inby the last full row of roof supports.

At approximately 2:05 p.m., Trimble was positioned between the roof bolting machine drill mast and the ATRS.  Witnesses stated that Trimble was attaching support wire to the previously installed wire roof screen and the piece of wire roof screen that would be installed.  A large piece of roof rock that measured 0.25 to 1.3 feet in thickness, 3 feet in width, and 11.5 feet in length, fell from the roof.  The rock fell in such a manner that the ATRS could not prevent the rock from hitting Trimble.  The edge of the rock closest to Trimble struck and pinned him in an upright position against the roof bolting machine drill canopy.

A. Mumau was operating the left side of the roof bolting machine.  He was looking toward the rear of the machine to ensure that the rear was not dragging on the bottom when he heard the rock fall.  A. Mumau turned around to find Trimble pinned by a rock against the drill canopy.  A. Mumua rushed outby shouting for help.  J. Mumau and scoop operators Paul Polenik and Cody Engle were loading a bridge conveyor onto a scoop just outby the last open crosscut in the number 2 entry. 

J. Mumau went to the roof bolting machine and returned to the last open crosscut to tell Polenik and Engle to not go to the accident scene because of the extent of the victim’s injuries.  He also instructed Engle to go to the intake entry and notify Barry Houser, Mine Foreman, about the accident.  Jeremiah Blake, Utility Man, was helping Frantz hang the continuous mining machine trailing cable in the number 4 entry when they heard shouting.  They went to the number 2 entry, where J. Mumau stopped them and told them to go to the intake with the rest of the crew.

Engle placed the call to the surface.  Paul Sieczkowski, Mine Clerk, received the call and told Houser that a man was hit by a rock.  Houser took the phone and asked about the extent of Trimble’s injuries.  Cody responded that he believed Trimble was dead.  Houser told Sieczkowski to notify MSHA and the State.  Thomas (Sammy) Bassaro, Mine Examiner, had completed his preshift examination and was on the surface.  He followed Houser to the section on a mantrip.

Justin Rebuck, Second Shift Section Foreman, arrived on the section.  J. Mumau told him about the accident.  Houser arrived, went to the accident scene, and walked outby to tell Bassaro to get a hydraulic pump jack from his mantrip.  Bassaro returned and gave the pump jack to Houser.  Houser boarded the roof bolting machine and set the pump jack against the roof bolting machine and the fallen rock. He used the jack to free the victim.

Houser, Rebuck, and J. Mumau transported the victim to the number 4 entry.  They placed him onto a mantrip and transported him to the surface.  Jerry L. Overman Jr., Coroner, and Steve Alexander, Deputy Coroner, arrived at the mine site where Overman pronounced the victim dead at 4:30 p.m.

INVESTIGATION OF THE ACCIDENT

At 2:19 p.m. on February 20, 2015, Sieczkowski notified the MSHA call center of the accident.  The call center notified Deborah Moberg, the District Manager’s Secretary, of the accident at 2:38 p.m.  David Weakland, Indiana Field Office Supervisor, issued a verbal 103(j) order to the mine operator at 3:00 p.m.  Richard Gray, Kittanning Field Office Supervisor; John Burda, Roof Control Specialist; James Miller, Coal Mine Inspector; Kerry Miller, Roof Control Specialist and Lead Accident Investigator; and Michael Gauna, Mining Engineer from MSHA’s Approval and Certification Center (AC&C), were notified and dispatched to the mine. 

Gray, Burda, and J. Miller arrived at the mine and obtained preliminary statements from persons with knowledge of the facts and circumstances concerning the accident.  Gray began reviewing mine tracking information.  Training records were requested and obtained from the mine operator.  K. Miller, Lead accident Investigator, arrived and modified the 103(j) order to a 103(k) order to ensure the safety of all persons during the accident investigation and to preserve all evidence at the accident scene.

Witness interviews were conducted on February 20, 2015, at the Heilwood Mine training area with persons that had knowledge of the facts and circumstances of the accident.  The MSHA investigators traveled underground along with inspectors from the Pennsylvania State Bureau of Mine Safety and mine officials.  Investigators photographed the accident scene and took measurements of the area and the roof bolting machine.

Additional interviews were conducted on February 23, 2015, with all roof bolters.  MSHA personnel also conducted second interviews with J. Mumau, Houser, and A. Mumau.

A list of the persons who participated in the investigation and those who were interviewed is contained in Appendix C.

Discussion

Accident Scene 
The accident occurred in the number 2 slope entry, approximately 170 feet inby survey station number 4794 in the A Mains section, MMU 001-0.  The mining height at the accident scene averaged 8.3 feet and the width of the number 2 entry was 19 feet.  The immediate mine floor consisted of gray shale, with pockets of shale bedding that were broken out forming undulations in the mine floor.  The mine ribs were in good condition, showing no signs of sloughage and consisted of shale partings throughout the mining height.

The last section of wire roof screen installed was not square with the number 2 entry.  The left side of the wire roof screen extended 20 inches inby the last row of permanent roof supports.  The right side of the wire roof screen panel extended 52 inches inby the last row of permanent roof supports.  Immediately outby, in the region above the roof bolting machine, steel channels with fully grouted bolts were installed where the spacing between each bolt ranged from 3.2 to 3.8 feet.  Channels with the vertical cable bolts were positioned between the channels installed with fully grouted roof bolts.

The rock that struck Trimble was found leaning against the main support of the ATRS, on the right side drill canopy and the other end on the mine floor with the inby edge approximately 5 inches outby the back edge of the ATRS.  The placement of the rock suggests that the rock did not contact the ATRS.  The rock measured 0.25 to 1.3 feet in thickness, 3 feet in width, and 11.5 feet in length.  The rock weighed approximately 4,400 pounds.  The rock was shaped similar to a parallelogram.

The roof bolting machine had not been moved when accident investigators arrived at the scene.  A pump jack was installed between the top of the drill canopy and the rock to free the victim.  The piece of wire roof screen that the victim and A. Mumau were preparing to install measured 5 feet wide by 14 feet in length.

Geological Conditions on the A Mains Section

Overburden at the accident site was approximately 690 feet.  No undermining or over mining with older workings exists in the vicinity of the slope.  The number 2 entry had been developed to the top of the Brookville Seam but had not yet reached the coal.  Weak bedding contacts are where layers of roof strata may separate from each other.  A 15 percent downward entry slope formed ledges in the roof as a result of the relatively horizontal bedding.  Because of the weak bedding contacts, as the mining cut is advanced down slope, roof stratum can peel away from other roof stratum until the roof strata is sufficiently thick enough to remain intact and not peel away.

In this manner, ledges or brows are formed in the roof.  The accident site where roof bolting was being conducted was in such a transition zone as the bolting was advancing towards a ledge in the mining cut.  The mine roof where roof bolts had been installed, the mine roof was the bottom of an overlying gray shale bed.  A general lack of continuous mining machine cutting bit marks in this roof for the last 8-foot distance of roof support installation indicated that the underlying gray shale bed easily peeled away from the overlying shale bed at the contact.

Inby the last installed roof support, a brow ran diagonally across the entry towards the inby right hand corner of the cut at roughly a 10° angle to the last installed roof support.  After the accident, the bottom exposed portion of the brow where the roof remained intact and where it was initially cut began roughly 4.5 feet from the left side rib.  The top exposed portion of the brow where it was in contact with the overlying shale bed began roughly 6 feet from the left pillar rib (see Appendix D).  The exposed surface of the brow, in the right side half of the entry, dipped inby towards the end of the cut at roughly 55° from horizontal, forming a roughly 2.5-foot wide exposed face that was created by the fallen rock.

Roof Control Plan and Addendum at Time of Accident

The last fully revised and consolidated roof control plan for this mine was approved on September 18, 2013.  A slope addendum was approved on September 17, 2014, for the procedures and precautions for development of three slopes from the lower Kittanning seam (B Seam) to the Brookville coal seam (A Seam).  The plan permitted a maximum mining width of 20 feet and required the roof to be supported with fully-grouted roof bolts at least 48 inches long in normal mining conditions.  The slope plan required the roof to be supported with fully-grouted roof bolts at least 72 inches long with stipulations that when encountering coal seams, bed separations, defective roof conditions, an obvious or predominant slip, or a visible clay vein fault, supplemental roof support will be installed.

The maximum cut depth was limited to 20 feet in the slope plan.  The maximum cut depth listed in the approved roof control plan was limited to 30 feet due to adverse roof conditions in the Lower Kittanning coal seam.  At the time of the accident, the mine operator had limited the cut depth to 10 feet because of adverse roof conditions and anticipated mining into the Brookville seam.  The Brookville seam had been mined in 2 of the 3 entries.  At the time of the accident the mine was in compliance with all measurements and distances required by the roof control plan slope addendum.

Roof Bolting Practices at this Mine
The primary roof supports on this section consisted of 6-foot long, fully grouted resin bolts, ¾ inches in diameter with a steel grade of “60” installed through a minimum T-3 channel.  The roof bolts were on a bolt pattern, with a maximum of 4 feet between bolts, a minimum of 4 bolts per row, and a maximum of 4 feet between rows.  The T-3 channel is a ribbed steel strap, 6-inch wide, up to approximately 18 feet long, that has holes through which roof bolts are installed. 

Between the primary supports, the operator was installing a row of supplemental roof supports. This consisted of cable bolts, truss bolts, and extra channels.  The operator installed the primary supports on 4 foot by 4 foot spacing, then backed the roof bolting machine up 2 feet to install the supplemental supports.  The primary and supplemental support rows consisted of 6 bolts in each row.  The primary and the supplemental supports were spaced apart on maximum 2 foot by 4 foot spacing, with the bolts installed on ends close to the ribs and approximately 2 feet from ribs.  The sections of wire roof screen were either contacting each other or overlapped with the supports installed through the screen.

Roof Bolting Machine
The equipment involved in the accident was a DDR-Dual Head, Mast Feed Roof  Drill, twin head roof bolting machine, model DDR-13-B, serial number 2011019, MSHA approval number 2G -2956A-6, manufactured by J.H. Fletcher and Company.  This machine has drill station canopies equipped with vertical slider extensions and also has angle drilling capability.  The ATRS system is an “L” style “T” bar with one ATRS pad in the middle and one on each end.  Each ATRS outer pads measured 16 inches long by 12 inches wide and the middle pad measured 18 inches long by 12 inches wide. This system was fitted with vertical extensions for the pads that measured 12 inches, and the middle extension measured 18 inches.

The width of the ATRS system is manually adjustable with four pin selections on each side, each six inches apart and measured 12 feet and 2 inches at the time of the accident. The pins were located in the second slot from the outside.

Testing was performed on the ATRS by AC&C.  Although not a factor in the accident, the lack of a pre-charge in the hydraulic accumulator and the high leakage rate of the check valve increased the likelihood that the ATRS would not provide proper roof support during a roof bolting cycle longer than 20 minutes.  A non-contributing citation was issued for this condition.   

The investigation revealed that at the time of the accident the middle extension of the ATRS beam was flipped forward in the stowed position.  The ATRS articulated beam was positioned at a relatively flat and level area of the mine roof.  With this roof geometry, and the outside two pads having the 12 inch extensions in place, the original middle pad could not contact the mine roof.  Only the two outside pads were in contact with the mine roof, with approximately a 9.5-foot distance between the inside edges of the two outer pads.  As previously stated, the rock fell between the ATRS and the last full row of roof supports and ATRS did not contact the rock that fell.  A non-contributing citation was issued for this condition.

Wire Roof Screen Installation Procedure
During the accident investigation interview process, it was discovered that the wire roof screen installation was not being conducted in a consistent manner by all roof bolters.  Four of the seven roof bolters stated that they walked in front of the drill mast to install support wire and felt that it was acceptable, since they said they were under the ATRS at all times.  However, during reenactment of the accident, it was determined, that the distance from the outby edge of the ATRS to the drill mast ranged from 18 to 22 inches.  At the time of the accident, the right hand canopy was approximately 4.3 feet off the mine floor and the left side canopy was approximately 4.5 feet off the mine floor.  The drill station canopies were lowered to place the wire roof screen on top of the canopies for installation.  This practice causes the drill station canopies to not be in a position to protect the roof bolters from potential roof hazards while positioning the wire roof screen.  As a result of the investigation, the mine’s roof control plan, was revised to include a safer means of installing wire roof screen.

Experience and Training

Trimble received his Pennsylvania Underground Miner Certification on March 7, 2012.  Based on records obtained from Rosebud Mining, Inc., Trimble had 3 years and 44 weeks of mining experience.  He began working at the Heilwood Mine 1 year and 12 weeks prior to the accident and worked the entire time as a roof bolter helper.

On November 18, 2013, Trimble received experienced miner training at the Heilwood Mine.  Trimble received task training for the roof bolting machine for the A Mains Section, on October 29, 2014.  On February 2, 2015 Trimble received annual refresher training.  No deficiencies for the victim’s training were found.

ROOT CAUSE ANALYSIS

A root cause analysis was conducted to identify the causes of the accident that were correctable through reasonable management controls.  Listed below are root causes identified during the analysis and the corresponding corrective actions implemented to prevent a reoccurrence of the accident.

  1. Root Cause: The mine operator failed to prevent miners from working in an area that was not adequately supported or otherwise controlled to prevent hazards from falling roof.  The roof bolting machine operators were allowed to position themselves between the drill mast and the ATRS, with the drill station canopies lowered, while positioning the roof screen.

Corrective Actions:

When welded wire mesh is being installed in conjunction with roof bolts:

  • Mesh panels will be positioned on the machine only while the machine is positioned under fully supported roof,
  • Mesh panels will be positioned over the drill stations and secured to the machine using at least two points of contact (e.g., drill steels raised through the mesh, wire/cable ties passed through the mesh and secured through holes in the ATRS pads, or mesh clamps affixed to the ATRS bar or pads).
  • If the mesh is dislodged as the bolting machine is trammed inby or as the ATRS is raised, the machine must be trammed outby under supported roof to reposition the panel.
  • It is also acceptable to install mesh panels over fully supported roof; in this application bolt length may be less than the minimum 6 ft length minimum prescribed in #1 above.
  1. The approved Roof Control Plan was revised to provide safer wire roof screen installation procedures and ATRS procedures during slope development.   All affected miners were trained in these procedures.

    ATRS procedures

    The ATRS Raise Control lever must be engaged for 5 seconds after the ATRS pads contact the roof and the corresponding gage must be observed to ensure that a minimum set pressure of 800 to 1,100 psi is achieved.

    When bolting, the maximum distance between the outby edge of the ATRS pads and the last row of permanent supports shall not exceed 5 ft.  The ATRS shall not be more than 18” from the center of the hole being drilled.

    The distance from the ATRS to each rib must not exceed 5 ft.  If due to unusual conditions, the distance between the ATRS and the rib exceeds 5 ft., the bolting machine must be positioned within 5 ft. of the rib on one side to allow safe installation of one bolt on that side while the off side operator remains in a permanently supported area.  Subsequent to bolt installation, the machine can be repositioned to complete the bolt row.

    Wire roof screen installation procedures

    4. During slope development, non-tensioned cable bolts are to be considered primary support if:

    • The cable bolt is part of a complete row of four bolts spaced no more than 30” beyond the 6 ft. primary row of bolts and,
    • The next row is the primary row of bolts.

CONCLUSION

The mine operator failed to prevent miners from working in an area that was not adequately supported or otherwise controlled to prevent hazards from falling roof.  The roof bolting machine operators were allowed to position themselves between the drill mast and the ATRS, with the drill station canopies lowered, while positioning the roof screen.  This practice exposed roof bolting machine operators to hazards from falling roof.

 

Approved By:
_________________________                 _________________ 
Thomas E. Light                                                     Date
District Manager

 

 

ENFORCEMENT ACTIONS

1. Order Number 8009988, was issued verbally by telephone at approximately 3:05 p.m. on February 20, 2015, under the provisions of section 103(j) of the Mine Act:

A fatal accident occurred at this operation on February 20, 2015, when a roof bolting machine operator was crushed by a roof rock while operating the right side of roof bolting machine. This order was issued to prevent the destruction of any evidence which would assist in the investigation of the cause or causes of the accident. The 103(j) Order, Number 8009988, was modified on February 20, 2015 to a 103(k) order at 5:07pm and was reduced to writing at 00:15 p.m. on February 21, 2015

2. Citation Number 8009990, was issued under the provisions of Section 104(a) of the Mine Act, for a violation of 30 CFR, § 75.202(a):

The operator failed to support or otherwise control an area of loose roof rock located in A Mains (MMU 001-0), approximately 180 feet inby survey station number 4794 in the number 2 entry. A roof rock fell between the last row of permanent support and the ATRS causing fatal crushing injuries. The rock measured 11.5 feet in length, averaging 1 foot in thickness and 3 feet wide along the majority of its length.

Standard 75.202(a) was cited 4 times in two years at mine 3609407 (4 to the operator, 0 to a contractor).


 

APPENDIX C
PERSONS PARTICIPATING IN THE ACCIDENT INVESTIGATION

Rosebud Mining Company

                          Name                                                   Title

J. Clifford Forrest                                     President 
Dave Doney                                              Mine Manager
Scott Troutman                                         Mine Superintendent

Barry Houser                                            Mine Foreman
Joe Zelanko                                              Manager of Engineering
Stanley Popich                                          Manager of Safety and Health
Joe Yuhas                                                 Company Attorney 
Ben Stock                                                 Company Attorney 
Jeremey Mumau*                                     Section Foreman
Arron Mumau*                                         Roof Bolting Machine Operator
Jim Frantz*                                               Operator
Luk Engle*                                               Shuttle Car Operator
Jeremy Blake*                                          Utility Man
Cody Engle*                                             Section Scoop Operator
Paul Polenik*                                           Section Scoop and Utility Man
Thomas Bassaro*                                     Beltman/Mine Examiner
Justin Rebuck*                                         Section Foreman

Matt Boozer*                                            Section Foreman

Alex Alkins*                                            Roof Bolting Machine Operator

Ryan Keith*                                              Roof Bolting Machine Operator

Jake Neal*                                                            Roof Bolting Machine Operator

Matt Fabbri*                                             Roof Bolting Machine Operator
Dave McConnell*                                    Maintenance Foreman
Joe Somogyi                                             Maintenance Supervisor

* Persons Interviewed

State Agency

                          Name                                                   Title

Joseph A. Sbaffoni                                   Bureau of Mine Safety Div.Chief
Robert DuBreucq                                      Supervisor
William Kokla                                          Underground Mine Inspector
Craig Carson                                             Chief Program Manager
Arthur Brower                                          Electrical Engineer Manager
Gary Smith                                               Mining Engineer Consultant

Jeff Kerch                                                 Chief Program Manager

Vince Little                                              Electrical Inspector

Appendix C Cont’d
Persons Participating in the Accident Investigation
Mine Safety and Health Administration

                          Name                                                   Title

Michael Gauna, PE                                   Mining Engineer/Accident Investigator

Richard Gray                                            Field Office Supervisor
James Miller                                             Coal Mine Inspector
John Burda                                                District 2 Roof Control Specialist
Kerry Miller                                             District 2 Roof Control Specialist

Steve Kotvas                                             Electrical Supervisor

T.Ashley McAfoose                                 Electrical Inspector

William Kibler                                         Electrical Inspector

James Angel                                             Mechanical Engineer

Juliette Hill                                               Accident Investigation Program Manager

Eugene Hennen                                         Mechanical Engineer